12035 W CLOVER AVE 90066
Certificate Information: 12035 W CLOVER AVE 90066
- Application / Permit
- 25014-10000-04231
- Plan Check / Job No.
- B25LA39403
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition (455 sf) to (E) Single Family Dwelling to rear of building . Work per Engineered Design .
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2025 | GEORGE ALVAREZ |
| Corrections Issued | 9/25/2025 | GEORGE ALVAREZ |
| Plan Check Approved | 12/2/2025 | GEORGE ALVAREZ |
| Issued | 12/2/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | ARAM AVEDISIAN |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/6/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 11/6/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2025 | JEFF LOREDO |
| Specific Plan | Cleared | 11/20/2025 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 12/2/2025 | GEORGE ALVAREZ |
Contact Information
| Contractor | Makeover Builders Inc.; Lic. No.: 986740-B | , |
| Contractor | Makeover Builders Inc; Lic. No.: 986740-B | , |
| Engineer | Babapirzadeh,, Ghazal; Lic. No.: C90480 | 7270 HILLSIDE AVE APT 306 LOS ANGELES, CA 90046 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2026 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/27/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/27/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/25/2026 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/25/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 2/25/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 2/25/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/25/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/3/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/3/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/3/2026 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/6/2026 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/18/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/18/2026 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 3/18/2026 | Approved | ARAM AVEDISIAN |
| Final | 5/18/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/18/2026 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Gas Company | KIRK SANDERS |
| Smoke Detectors | 5/18/2026 | Approved | KIRK SANDERS |
| Final | 5/21/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 5/21/2026 | Approved | ARAM AVEDISIAN |