5860 W 18TH ST 90019
Certificate Information: 5860 W 18TH ST 90019
- Application / Permit
- 25014-10000-04194
- Plan Check / Job No.
- B25LA38997
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - ADDITION AND CONVERSION OF EXISTING GARAGE TO ADU PER GC 66323(a)(4)(a)(ii) WITH ROOF TOP DECK
- Permit Issued
- Issued on 3/9/2026
- Issuing Office
- Current Status
- Issued on 3/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | STARR CHEN |
| Corrections Issued | 9/29/2025 | STARR CHEN |
| Quality Review Completed | 9/30/2025 | EUGENE BARBEAU |
| Assigned to Zoning Architect | 10/2/2025 | KAREN MEZA-MORALES |
| Plan Check Approved | 1/30/2026 | STARR CHEN |
| Issued | 3/9/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 10/9/2025 | SAFA JAVANMARDI |
| CPC | Cleared | 10/24/2025 | GEORGIA SMITH |
| CPC | Cleared | 10/24/2025 | GEORGIA SMITH |
| Construction near power lines | Cleared | 11/7/2025 | RIDWAN HARDY |
| Zoning Plan Check | Cleared | 12/9/2025 | KAREN MEZA-MORALES |
| Hold | Cleared | 3/19/2026 | MARIA VENDIVIL |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: NA37588 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2026 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 4/1/2026 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/27/2026 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 6/2/2026 | Approved | RONNIE MINDANAO |
| Sewer | 6/2/2026 | Approved | RONNIE MINDANAO |