229 N BOWLING GREEN WAY 90049
Certificate Information: 229 N BOWLING GREEN WAY 90049
- Application / Permit
- 25014-10000-04188
- Plan Check / Job No.
- B25LA38976
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE AND RUMPUS ROOM INTO ADU WITH NEW ADDITION PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 11/7/2025
- Issuing Office
- Current Status
- Issued on 11/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2025 | JOHNPAUL ISIP |
| Corrections Issued | 9/22/2025 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 10/10/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 10/16/2025 | JOHNPAUL ISIP |
| Issued | 11/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction within easement | Cleared | 9/24/2025 | EDGAR PASCUA |
| Address approval | Cleared | 9/25/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/25/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 9/29/2025 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 10/9/2025 | STEVE MELGAR |
Contact Information
| Contractor | Adar Builders Inc; Lic. No.: 1051859-B | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: NA82330 | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/10/2025 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/12/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/20/2026 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 1/20/2026 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 1/20/2026 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 2/6/2026 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 2/6/2026 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 2/6/2026 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 2/6/2026 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 2/6/2026 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 2/18/2026 | Approved | EVAN COOPER |
| HVAC-Rough | 2/18/2026 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 2/18/2026 | Approved | EVAN COOPER |
| Gas Test | 2/20/2026 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 2/20/2026 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/11/2026 | Conditional Approval | EVAN COOPER |
| Deputy Wood Construction | 3/11/2026 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 3/11/2026 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 3/17/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/17/2026 | Partial Approval | EVAN COOPER |
| Shower Pan | 3/17/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 4/3/2026 | Approved | CHRISTOPHER WILSON |