5213 N EAGLE ROCK BLVD 90041
Certificate Information: 5213 N EAGLE ROCK BLVD 90041
- Application / Permit
- 25014-10000-04132
- Plan Check / Job No.
- B25LA38574
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1ST AND 2ND FLOOR ADDTION TO (E) DETACHED GARAGE TO HAVE 2-STORY ADU LAMC 12.22 A.33(b)(1) WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 4/2/2026
- Issuing Office
- Metro
- Current Status
- Issued on 4/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | MAHNAZ NOURHASHEMI |
| Assigned to Zoning Architect | 9/25/2025 | NICHOLE MACOY |
| Corrections Issued | 10/2/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/8/2025 | KEN GILL |
| Building Plans Picked Up | 10/9/2025 | APPLICANT |
| Plan Check Approved | 4/2/2026 | MAHNAZ NOURHASHEMI |
| Issued | 4/2/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 10/14/2025 | DAVID LOPEZ |
| Zoning Plan Check | Cleared | 1/7/2026 | NICHOLE MACOY |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2026 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 1/9/2026 | ROSE STEIN-WENDT |
| Construction near power lines | Cleared | 4/2/2026 | AARON DIZON |
| Construction within easement | Cleared | 4/2/2026 | AARON DIZON |
| GPI Written Notices | Cleared | 4/2/2026 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 4/2/2026 | RAMAZANALI ALMASI |
Contact Information
| Contractor | Felix Construction Group Inc; Lic. No.: 886840-B | 1147 W 9TH STREET UPLAND, CA 91786 |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/20/2026 | Partial Approval | RONNIE MEDINA |
| Footing/Foundation/Slab | 4/30/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/1/2026 | Partial Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/7/2026 | Approved | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Partial Approval | RONNIE MEDINA |