1788 S CORNING ST 90035
Certificate Information: 1788 S CORNING ST 90035
- Application / Permit
- 25014-10000-04117
- Plan Check / Job No.
- B25LA38394
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Current Status
- Issued on 10/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2025 | CARLOS MONTES |
| Corrections Issued | 9/17/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 9/23/2025 | TSE MING HUANG |
| Plan Check Approved | 10/1/2025 | CARLOS MONTES |
| Issued | 10/3/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2025 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 9/22/2025 | JEREMY CHOK |
| Hold | Cleared | 11/17/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/20/2025 | Conditional Approval | EVAN COOPER |
| METHANE-Barrier | 11/21/2025 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 11/21/2025 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 11/25/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 11/25/2025 | Partial Approval | MICHAEL ALLEN |
| Underground Mechanical | 11/25/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 12/9/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Rough | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| METHANE-Rough | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| Sewer | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| Wood Frame | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 3/9/2026 | Not Ready for Inspection | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Corrections Issued | WILBER ROSALES |
| HVAC-Rough | 3/9/2026 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Rough | 3/9/2026 | Not Ready for Inspection | WILBER ROSALES |
| Rough-Elec/Plmb/HVAC | 3/9/2026 | Not Ready for Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/16/2026 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 3/16/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 3/16/2026 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 3/16/2026 | Approved | WILBER ROSALES |
| METHANE-Rough | 3/16/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 3/16/2026 | Not Ready for Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/18/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 3/18/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 3/18/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 3/18/2026 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 3/18/2026 | Approved | WILBER ROSALES |
| Insulation | 3/24/2026 | Approved | WILBER ROSALES |
| Drywall Nailing | 4/1/2026 | Not Ready for Inspection | WILBER ROSALES |
| Shower Pan | 4/1/2026 | Not Ready for Inspection | WILBER ROSALES |
| Drywall Nailing | 4/13/2026 | Approved | WILBER ROSALES |
| Shower Pan | 4/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| Interior/Exterior Lathing | 4/22/2026 | Approved | WILBER ROSALES |
| Shower Pan | 4/22/2026 | Corrections Issued | WILBER ROSALES |
| Shower Pan | 4/27/2026 | Approved | WILBER ROSALES |