8121 N WHITE OAK AVE 91335
Certificate Information: 8121 N WHITE OAK AVE 91335
- Application / Permit
- 25014-10000-04055
- Plan Check / Job No.
- B25LA37682
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) S.F.D. *NFPA -13D Fire Sprinklers*
- Permit Issued
- Issued on 12/3/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | JESSE VIDUYA |
| Assigned to Zoning Architect | 9/18/2025 | DAVID ZHENG |
| Corrections Issued | 9/26/2025 | JESSE VIDUYA |
| Quality Review Completed | 10/2/2025 | KEN GILL |
| Building Plans Picked Up | 10/29/2025 | APPLICANT |
| Plan Check Approved | 11/21/2025 | JESSE VIDUYA |
| Issued | 12/3/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/14/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2025 | WALLIE JONG |
| Sewer availability | Cleared | 11/20/2025 | WALLIE JONG |
| Zoning Plan Check | Cleared | 11/20/2025 | DAVID ZHENG |
Contact Information
| Contractor | Suchite J C Construction; Lic. No.: 1020926-B | 22308 LANARK STREET CANOGA PARK, CA 91304 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/22/2026 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/28/2026 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/11/2026 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 3/11/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 3/11/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/11/2026 | Approved | ARUTYUN MADATYAN |
| Insulation | 3/20/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/20/2026 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 3/24/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/14/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/14/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 5/14/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 5/14/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/14/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 5/14/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/26/2026 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Final | 5/26/2026 | Approved | ARUTYUN MADATYAN |