3642 1/2 E PERCY ST 90023

Certificate Information: 3642 1/2 E PERCY ST 90023

Application / Permit
25014-10000-04041
Plan Check / Job No.
B25LA37498
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition to (E) Single Family Dwelling Per WFPP.
Permit Issued
Issued on 10/7/2025
Issuing Office
Current Status
CofO Issued on 2/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2025 APPLICANT
Assigned to Plan Check Engineer 9/10/2025 NEHEMIAS RAMOS
Corrections Issued 9/11/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 10/2/2025 TSE MING HUANG
Plan Check Approved 10/7/2025 NEHEMIAS RAMOS
Issued 10/7/2025 APPLICANT
CofO in Progress 2/9/2026 FREDDIE RIVERA
Permit Finaled 2/10/2026 DEROLD HAUFF
CofO Issued 2/10/2026 DEROLD HAUFF
Permit Finaled 2/10/2026 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 9/19/2025 JASON CHAN
Roof/Waste drainage to street Cleared 9/22/2025 ROSE STEIN-WENDT
Sewer availability Cleared 9/22/2025 ROSE STEIN-WENDT
Eng Process Fee Ord 176,300 Cleared 9/23/2025 ROSE STEIN-WENDT

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2025 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/31/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 11/7/2025 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 11/12/2025 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval SCOTT FINNILA
Insulation 11/12/2025 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/21/2025 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 12/8/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 12/11/2025 Approved ANTHONY RAMOS
HVAC-Rough 12/11/2025 Approved ANTHONY RAMOS
PLUMBING-Rough 12/11/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 12/12/2025 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 12/15/2025 Partial Inspection FREDDIE RIVERA
Insulation 12/15/2025 Approved FREDDIE RIVERA
Drywall Nailing 12/19/2025 Approved JUSTIN HAWLEY
Green Building Rough 12/19/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/19/2025 Approved JUSTIN HAWLEY
Shower Pan 12/19/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/22/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 2/2/2026 Approved JUSTIN HAWLEY
Final 2/2/2026 Corrections Issued JUSTIN HAWLEY
Special/Order Compliance 2/2/2026 Partial Inspection OSVALDO PARAMO
Final 2/6/2026 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 2/6/2026 Approved FREDDIE RIVERA