6212 S FLORES AVE 90056
Certificate Information: 6212 S FLORES AVE 90056
- Application / Permit
- 25014-10000-04031
- Plan Check / Job No.
- B25LA37467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Covert (e) detached garage (360sf) into ADU with 150sf addition per GC 66323(a)(2). Work per WFPP
- Permit Issued
- Issued on 3/24/2026
- Issuing Office
- Current Status
- Issued on 3/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2025 | DANIEL SMILEY |
| Corrections Issued | 9/23/2025 | DANIEL SMILEY |
| Applicant returned to address corrections | 2/23/2026 | AUNG SOE |
| Plan Check Approved | 2/23/2026 | AUNG SOE |
| Issued | 3/24/2026 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/10/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/10/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 12/15/2025 | ROBERT PINA |
| Address approval | Cleared | 12/26/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 2/2/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 2/5/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Mcinc Construction Inc; Lic. No.: 1087192-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/25/2026 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 4/1/2026 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 4/9/2026 | No Access for Inspection | ANTHONY EGSON |
| Underground Mechanical | 4/15/2026 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 4/20/2026 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 4/20/2026 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 5/14/2026 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 5/14/2026 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 5/14/2026 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 5/14/2026 | Approved | MICHAEL LEWIS |
| Insulation | 6/1/2026 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/1/2026 | Approved | MICHAEL LEWIS |
| Insulation | 6/4/2026 | Partial Inspection | MICHAEL LEWIS |
| Wood Frame | 6/4/2026 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 6/11/2026 | Approved | EUGENE CASSIDY |
| Wood Frame | 6/11/2026 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/17/2026 | Approved | ANTHONY EGSON |