- Permit Issued
- Issued on 1/13/2026
- Issuing Office
- Current Status
- Issued on 1/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | KHUONG TRUONG |
| Assigned to Zoning Architect | 9/11/2025 | ELAHE MERRIKHI |
| Corrections Issued | 9/13/2025 | KHUONG TRUONG |
| Quality Review Completed | 9/19/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/2/2025 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/20/2025 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/22/2025 | KHUONG TRUONG |
| Plan Check Approved | 1/12/2026 | KHUONG TRUONG |
| Issued | 1/13/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | CELINA MORENO |
| Sewer availability | Cleared | 9/25/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/7/2025 | CELINA MORENO |
| Zoning Plan Check | Cleared | 10/14/2025 | ERIK VILLANUEVA |
| Construction near power lines | Cleared | 1/12/2026 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2026 | Corrections Issued | JEFFREY MEAD |
| METHANE-Barrier | 1/29/2026 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 1/29/2026 | Approved | JEFFREY MEAD |
| Underground Mechanical | 1/29/2026 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Partial Approval | JEFFREY MEAD |