8332 S TRUXTON AVE 90045

Certificate Information: 8332 S TRUXTON AVE 90045

Application / Permit
25014-10000-03946
Plan Check / Job No.
B25LA36662
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] 1ST AND 2ND FLOOR ADDITION TO (E) GARAGE TO CONVERT TO ADU PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 12/1/2025
Issuing Office
Current Status
Issued on 12/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/3/2025 APPLICANT
Assigned to Plan Check Engineer 9/11/2025 MAHNAZ NOURHASHEMI
Corrections Issued 9/23/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 10/1/2025 TU HUA
Applicant returned to address corrections 11/7/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 11/25/2025 MAHNAZ NOURHASHEMI
Issued 12/1/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/7/2025 ENRIQUE ACOSTA
Construction within easement Cleared 10/7/2025 ENRIQUE ACOSTA
Address approval Cleared 10/13/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 10/13/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 10/21/2025 JESUS CISNEROS
Sewer availability Cleared 10/21/2025 JESUS CISNEROS
Specific Plan Cleared 10/27/2025 MOHAMMAD HASAN

Contact Information

Architect Erlich,, Ayal; Lic. No.: C36241 5026 KINGSPINE RD      ROLLING HILLS ESTATES, CA 90274
Architect Erlich,, Ayal; Lic. No.: NA36241       ,
Contractor Vertex Developers Inc; Lic. No.: 962652-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2026 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 4/15/2026 Corrections Issued JESUS PINEDA
PLUMBING-Rough 4/15/2026 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 5/4/2026 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 5/4/2026 Not Ready for Inspection JESUS PINEDA
Sewer 5/4/2026 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 5/7/2026 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/7/2026 Partial Approval JESUS PINEDA