3208 N INGLEDALE TER 90039
Certificate Information: 3208 N INGLEDALE TER 90039
- Application / Permit
- 25014-10000-03844
- Plan Check / Job No.
- B25LA33308
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN - CONVERSION AND ADDITION TO (E) DETACHED GARAGE TO CREATE ADU PER GC 66323(a)(2)
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Current Status
- Issued on 11/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | JOSEPH RAFOLS |
| Corrections Issued | 8/25/2025 | JOSEPH RAFOLS |
| Quality Review Completed | 9/4/2025 | HERNAN ARREOLA |
| Plan Check Approved | 10/23/2025 | JOSEPH RAFOLS |
| Issued | 11/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 9/8/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/10/2025 | DAVID LOPEZ |
| Construction near power lines | Cleared | 9/17/2025 | ENRIQUE ACOSTA |
| ZI | Cleared | 9/22/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Sweiskloss Inc; Lic. No.: 766542-B | , |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/4/2026 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 2/10/2026 | Conditional Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 2/10/2026 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 3/4/2026 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 5/21/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 5/21/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 5/21/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 5/21/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 5/21/2026 | Approved | NICHOLAS LOPEZ |