707-709 N ILIFF ST 90272
Certificate Information: 707-709 N ILIFF ST 90272
- Application / Permit
- 25014-10000-03842
- Plan Check / Job No.
- B25LA35639
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **2025 WILDFIRE PROJECT INELIGIBLE** REMODEL (E) SFD AND 2ND FLOOR ADU ADDITION. maintain portion of existing bldg
- Permit Issued
- Issued on 3/5/2026
- Issuing Office
- Current Status
- Issued on 3/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | JOE VO |
| Corrections Issued | 9/14/2025 | JOE VO |
| Quality Review Completed | 9/23/2025 | GARO TELMI |
| Plan Check Approved | 12/15/2025 | JOE VO |
| Issued | 3/5/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 10/6/2025 | JERRY KAO |
| GPI Written Notices | Cleared | 11/20/2025 | JOE VO |
| Address approval | Cleared | 11/21/2025 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 12/6/2025 | RUSSELL BONVOULOIR |
Contact Information
| Contractor | Line Electric Inc; Lic. No.: 910172-B | , |
| Engineer | Gupta,, Raghu; Lic. No.: C87913 | 38725 LEXINGTON ST APT 150 FREMONT, CA 94536 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/23/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/3/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/9/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2026 | Corrections Issued | DANIEL VERA |
| Deputy Drilled-In Anchors | 4/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 5/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2026 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/20/2026 | Approved | JESUS PINEDA |
| HVAC-Rough | 5/20/2026 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 5/20/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/28/2026 | Partial Approval | JESUS PINEDA |
| Insulation | 5/28/2026 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 6/1/2026 | No Result Entered | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/8/2026 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 6/8/2026 | Corrections Issued | ARAM AVEDISIAN |