1617 S OGDEN DR 90019

Certificate Information: 1617 S OGDEN DR 90019

Application / Permit
25014-10000-03788
Plan Check / Job No.
B25LA35142
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODELING AND ADDITION OF EXISTING SFR
Permit Issued
Issued on 2/27/2026
Issuing Office
Current Status
Issued on 2/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/22/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 YILE TIAN
Assigned to Zoning Architect 8/28/2025 NICHOLE MACOY
Corrections Issued 9/11/2025 YILE TIAN
Quality Review Completed 10/6/2025 HERNAN ARREOLA
Applicant returned to address corrections 1/15/2026 YILE TIAN
Plan Check Approved 2/19/2026 YILE TIAN
Issued 2/27/2026 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/1/2025 ENRIQUE ACOSTA
CPC Cleared 10/6/2025 MATHEW QUAN
CPC Cleared 10/6/2025 MATHEW QUAN
Roof/Waste drainage to street Cleared 10/8/2025 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/27/2025 ABEL CASILLAS
Sewer availability Cleared 10/27/2025 ABEL CASILLAS
Zoning Plan Check Cleared 11/5/2025 NICHOLE MACOY

Contact Information

Contractor Castillo Construction Services Inc; Lic. No.: 1076756-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/26/2026 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 3/26/2026 Not Ready for Inspection BRENDAN MORELLI
METHANE-Barrier 3/26/2026 Approved BRENDAN MORELLI
METHANE-Subgrade 3/26/2026 Approved BRENDAN MORELLI
Special/Order Compliance 3/26/2026 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 3/27/2026 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 3/31/2026 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 4/3/2026 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 4/3/2026 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/6/2026 Partial Approval BRENDAN MORELLI
Insulation 4/6/2026 Partial Approval BRENDAN MORELLI
METHANE-Rough 4/6/2026 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 4/9/2026 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/13/2026 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/14/2026 Partial Approval DAVID WILLIAMS
HVAC-Rough 5/14/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 5/14/2026 Corrections Issued DAVID WILLIAMS
BUILDING-Rough-Frame 5/15/2026 Not Ready for Inspection DAVID WILLIAMS
Green Building Rough 5/15/2026 Not Ready for Inspection DAVID WILLIAMS
HVAC-Rough 5/15/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 5/15/2026 Approved DAVID WILLIAMS
ELECTRICAL-Rough 5/19/2026 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/19/2026 Corrections Issued DAVID WILLIAMS
HVAC-Rough 5/19/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 5/19/2026 Approved DAVID WILLIAMS
Wood Frame 5/19/2026 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 5/20/2026 Approved DAVID WILLIAMS
ELECTRICAL-Rough 5/20/2026 Approved DAVID WILLIAMS
Green Building Rough 5/20/2026 Approved DAVID WILLIAMS
Insulation 5/26/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 5/26/2026 Partial Approval DAVID WILLIAMS
Drywall Nailing 5/29/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 5/29/2026 Not Ready for Inspection DAVID WILLIAMS
Interior/Exterior Lathing 6/2/2026 Approved BRIAN SULLIVAN
Shower Pan 6/2/2026 Approved BRIAN SULLIVAN