542 N SAN BENITO ST 90033

Certificate Information: 542 N SAN BENITO ST 90033

Application / Permit
25014-10000-03775
Plan Check / Job No.
B25LA34982
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: 2nd story Room addition with new Bathroom to (e) adu per GC66323(a)(4)
Permit Issued
Issued on 12/14/2025
Issuing Office
Current Status
CofO Issued on 7/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 RACHEL BEYENE
Corrections Issued 8/29/2025 RACHEL BEYENE
Quality Review Completed 9/24/2025 HERNAN ARREOLA
Applicant returned to address corrections 10/14/2025 RACHEL BEYENE
Applicant returned to address corrections 11/12/2025 RACHEL BEYENE
Plan Check Approved 12/11/2025 RAHEL BEYENE
Issued 12/14/2025 APPLICANT
CofO in Progress 7/9/2026 OSVALDO PARAMO
Permit Finaled 7/11/2026 DEROLD HAUFF
CofO Issued 7/11/2026 DEROLD HAUFF
Permit Finaled 7/11/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/25/2025 ADRIAN SANCHEZ
Sewer availability Cleared 9/25/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 10/21/2025 PAMELA TENEZA
Grading Pre-Inspection Cleared 12/11/2025 RAMAZANALI ALMASI

Contact Information

Contractor Jkc Construction & Design; Lic. No.: 1007078-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/26/2026 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 3/13/2026 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/13/2026 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/13/2026 Partial Approval ALIZAH MAYAGOITIA
MERV13>=Rough 3/13/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 3/13/2026 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 3/31/2026 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 4/3/2026 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 4/3/2026 Conditional Approval ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 4/3/2026 Approved ALIZAH MAYAGOITIA
Insulation 4/10/2026 Corrections Issued ALIZAH MAYAGOITIA
Insulation 4/13/2026 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/13/2026 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 4/15/2026 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/20/2026 Approved ALIZAH MAYAGOITIA
Shower Pan 4/20/2026 Approved ALIZAH MAYAGOITIA
Final 6/11/2026 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 6/11/2026 Approved OSVALDO PARAMO
MERV13>=Final 6/11/2026 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/11/2026 SGSOV Not Ready OSVALDO PARAMO
Sewer 6/11/2026 Approved OSVALDO PARAMO
Smoke Detectors 6/11/2026 Not Ready for Inspection OSVALDO PARAMO
Final 6/25/2026 Corrections Issued OSVALDO PARAMO
MERV13>=Final 6/25/2026 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/25/2026 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 6/25/2026 Approved OSVALDO PARAMO
Final 7/6/2026 OK to Issue CofO OSVALDO PARAMO