15971 W SKYTOP ROAD 91436

Certificate Information: 15971 W SKYTOP ROAD 91436

Application / Permit
25014-10000-03770
Plan Check / Job No.
B25LA34863
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 24014-10000- 02996 TO CAPTURE REMODEL/ADDITION REVISIONS ON THE PLAN. - UPDATE THE USE CODE SECTION TO SHOW THE CORRECT USE FOR THIS BLDG.
Permit Issued
Issued on 1/29/2026
Issuing Office
Current Status
Issued on 1/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/20/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 MAHNAZ NOURHASHEMI
Corrections Issued 9/10/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 9/18/2025 TU HUA
Applicant returned to address corrections 10/16/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 10/28/2025 MAHNAZ NOURHASHEMI
Assigned to Zoning Architect 11/6/2025 NEVRIK NAVASARTIAN
Plan Check Approved 1/29/2026 MAHNAZ NOURHASHEMI
Issued 1/29/2026 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/11/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 12/11/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 12/11/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 12/11/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 12/11/2025 DAVID LOPEZ
Sewer availability Cleared 12/11/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/12/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 12/12/2025 JOHN CONNEALLY
BHO/Hillside ordinance Cleared 1/20/2026 JESUS LUNA
Grading Pre-Inspection Cleared 1/21/2026 CHARLES POWELL
Zoning Plan Check Cleared 1/27/2026 NEVRIK NAVASARTIAN

Contact Information

Architect Horwitz,, Dulcie Elaine; Lic. No.: NA28941       ,
Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/12/2026 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 2/12/2026 Approved JOHN KIDWELL
Footing/Foundation/Slab 2/12/2026 Approved JOHN KIDWELL
Pre-Inspection 3/26/2026 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 4/8/2026 Not Ready for Inspection THOMAS FINNILA
Wood Frame 4/8/2026 Partial Approval THOMAS FINNILA
Green Building Rough 4/10/2026 Not Ready for Inspection THOMAS FINNILA
Wood Frame 4/10/2026 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/28/2026 Partial Approval JOHN KIDWELL