5403 N KATHERINE AVE 91401
Certificate Information: 5403 N KATHERINE AVE 91401
- Application / Permit
- 25014-10000-03739
- Plan Check / Job No.
- B25LA34616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. New SFD per SB9 above existing garage with balcony.
- Permit Issued
- Issued on 2/10/2026
- Issuing Office
- Current Status
- Issued on 2/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | MIGUEL LOPEZ |
| Corrections Issued | 10/7/2025 | MIGUEL LOPEZ |
| Quality Review Completed | 10/17/2025 | JOHNNY WU |
| Applicant returned to address corrections | 1/15/2026 | MIGUEL LOPEZ |
| Applicant returned to address corrections | 1/29/2026 | MIGUEL LOPEZ |
| Plan Check Approved | 2/9/2026 | MIGUEL LOPEZ |
| Issued | 2/10/2026 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/12/2025 | GEVORK KARAPETYAN |
| Address approval | Cleared | 1/2/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 1/2/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 1/5/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/6/2026 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/13/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/27/2026 | Approved | VINCENT HANLEY |
| Sewer | 5/5/2026 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/5/2026 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/15/2026 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/20/2026 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/27/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/27/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/27/2026 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/27/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/27/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 5/27/2026 | Approved | VINCENT HANLEY |
| Insulation | 6/2/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/5/2026 | No Result Entered | VINCENT HANLEY |