2226 N RIVERDALE AVE 90031

Certificate Information: 2226 N RIVERDALE AVE 90031

Application / Permit
25014-10000-03720
Plan Check / Job No.
B25LA34429
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN, REMOVE EXISTING ATTACHED PATIO COVER AND PROPOSE NEW ADDITIONS TO EXISTING ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
Permit Issued
Issued on 10/21/2025
Issuing Office
Current Status
Issued on 10/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Plan Check Engineer 8/21/2025 MADISON ODELL
Corrections Issued 8/21/2025 MADISON ODELL
Applicant returned to address corrections 10/6/2025 MINA HABILI
Plan Check Approved 10/18/2025 MINA HABILI
Issued 10/21/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 9/8/2025 DALIA MOKAYED
Roof/Waste drainage to street Cleared 9/13/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 9/16/2025 DERRICK MAGEE

Contact Information

Contractor Cali Luxury Builders Inc; Lic. No.: 1127045-B       ,
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/19/2025 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/19/2025 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/12/2026 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/20/2026 No Access for Inspection WILLIAM SIERRA
Special/Order Compliance 1/20/2026 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/19/2026 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/19/2026 Approved HAMIK HARTOUNIAN
Green Building Rough 3/19/2026 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 3/19/2026 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 3/19/2026 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/3/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 4/3/2026 Approved HAMIK HARTOUNIAN
MERV13>=Rough 4/3/2026 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/15/2026 Partial Approval GEM DE OCAMPO
BUILDING-Rough-Frame 4/21/2026 Approved HAMIK HARTOUNIAN
Insulation 4/27/2026 Approved GEM DE OCAMPO
Drywall Nailing 5/4/2026 Approved GEM DE OCAMPO