616 N LAS LOMAS AVE 90272
Certificate Information: 616 N LAS LOMAS AVE 90272
- Application / Permit
- 25014-10000-03708
- Plan Check / Job No.
- B25LA34280
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 3-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO1 EXISTING FOUNDATION TO REMAIN
- Permit Issued
- Issued on 1/12/2026
- Issuing Office
- Current Status
- Issued on 1/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | EDWIN ESPIN |
| Corrections Issued | 8/23/2025 | JAD BASMA |
| Quality Review Completed | 9/8/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/19/2025 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/1/2025 | EDWIN ESPIN |
| Plan Check Approved | 12/28/2025 | EDWIN ESPIN |
| Issued | 1/12/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Coastal Zone | Cleared | 9/29/2025 | BRENNEN OBETO |
| ZA Case | Cleared | 9/29/2025 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 10/24/2025 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 11/19/2025 | JAD BASMA |
| GPI Written Notices | Cleared | 12/28/2025 | JAD BASMA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Pagan Robert M Construction Company; Lic. No.: 509594-B | , |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2026 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2026 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 5/12/2026 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Corrections Issued | MICHAEL ALLEN |