3021 S KELTON AVE 90034
Certificate Information: 3021 S KELTON AVE 90034
- Application / Permit
- 25014-10000-03664
- Plan Check / Job No.
- B25LA33809
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. MAJOR REMODEL TO EXISTING 1-STORY SFD WITH 1-STORY ADDITION AND (N) ATTACHED TRELLIS AT REAR, EXISTING 2-CAR GARAGE WILL REMAIN. TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGH OUT.
- Permit Issued
- Issued on 10/23/2025
- Issuing Office
- Current Status
- CofO Issued on 4/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | ADRIANA LOPEZ |
| Corrections Issued | 9/2/2025 | ADRIANA LOPEZ |
| Quality Review Completed | 9/24/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 10/14/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 10/22/2025 | ADRIANA LOPEZ |
| Issued | 10/23/2025 | APPLICANT |
| CofO in Progress | 4/24/2026 | ASHLEY THOMPSON |
| Permit Finaled | 4/27/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/27/2026 | RICHARD STEINBACH |
| CofO Issued | 4/27/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/13/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 9/15/2025 | DERRICK MAGEE |
| Grading Pre-Inspection | Cleared | 9/22/2025 | LANNY MERRICK |
| Specific Plan | Cleared | 10/16/2025 | PEDRO AYALA |
| GPI Written Notices | Cleared | 10/22/2025 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kashe,, Andrew; Lic. No.: C94117 | 984 SILVERTIP DR DIAMOND BAR, CA 91765 |
| Engineer | Kashe,, Andrew; Lic. No.: NA94117 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 11/5/2025 | Approved | KIRK SANDERS |
| Underground Mechanical | 11/5/2025 | Partial Approval | KIRK SANDERS |
| Wood Frame | 11/5/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Partial Approval | MICHAEL ALLEN |
| Gas Test | 11/6/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/25/2025 | Corrections Issued | KIRK SANDERS |
| Final | 11/25/2025 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Partial Approval | KIRK SANDERS |
| Gas Test | 12/4/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 12/4/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 12/8/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 12/10/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 12/10/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 12/10/2025 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/16/2025 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/16/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/22/2025 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 12/22/2025 | Approved | KIRK SANDERS |
| Green Building Rough | 12/22/2025 | Approved | KIRK SANDERS |
| MERV13>=Rough | 12/22/2025 | Approved | KIRK SANDERS |
| Shower Pan | 12/22/2025 | Approved | KIRK SANDERS |
| Wood Frame | 12/22/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/26/2025 | Approved | KIRK SANDERS |
| Insulation | 12/26/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/26/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 12/30/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 3/10/2026 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 3/10/2026 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/12/2026 | Approved | ARAM AVEDISIAN |
| Final | 3/12/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/12/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 3/12/2026 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 3/12/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 3/12/2026 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/12/2026 | Approved | ARAM AVEDISIAN |
| Final | 4/22/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| Service/Power Release | 4/22/2026 | Approved | ASHLEY THOMPSON |