15609 W HUSTON ST 91436
Certificate Information: 15609 W HUSTON ST 91436
- Application / Permit
- 25014-10000-03613
- Plan Check / Job No.
- B25LA33310
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing attached covered patio (394 sf) to livable space at rear of (E) S.F.D. w./ att. garage
- Permit Issued
- Issued on 10/1/2025
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2025 | CAROLEAN BASMA |
| Corrections Issued | 8/15/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 9/3/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 9/17/2025 | CAROLEAN BASMA |
| Plan Check Approved | 10/1/2025 | CAROLEAN BASMA |
| Issued | 10/1/2025 | APPLICANT |
| No Progress | 3/24/2026 | THOMAS FINNILA |
| CofO in Progress | 3/24/2026 | THOMAS FINNILA |
| Permit Finaled | 3/26/2026 | JOHN JANSON |
| CofO Issued | 3/26/2026 | JOHN JANSON |
| Permit Finaled | 3/26/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/25/2025 | CINDY QI |
| Sewer availability | Cleared | 8/25/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2025 | CINDY QI |
Contact Information
| Contractor | Euro26 And Associates Inc; Lic. No.: 842541-B | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/16/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 10/27/2025 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 11/10/2025 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/25/2025 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 11/25/2025 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/4/2025 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 12/4/2025 | Approved | THOMAS FINNILA |
| HVAC-Rough | 12/4/2025 | Approved | THOMAS FINNILA |
| Drywall Nailing | 12/10/2025 | Approved | THOMAS FINNILA |
| Gas Test | 12/10/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/10/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/16/2025 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/11/2026 | Partial Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 2/11/2026 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 2/11/2026 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 2/11/2026 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | THOMAS FINNILA |
| Final | 2/27/2026 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 2/27/2026 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 2/27/2026 | Approved | THOMAS FINNILA |
| Final | 3/10/2026 | Partial Approval | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | JACK KARGODORIAN |
| Final | 3/24/2026 | Corrections Issued | THOMAS FINNILA |
| Final | 3/25/2026 | OK to Issue CofO | THOMAS FINNILA |