4518 N WORTSER AVE 91604

Certificate Information: 4518 N WORTSER AVE 91604

Application / Permit
25014-10000-03598
Plan Check / Job No.
B25LA33125
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: House remodel and additions (130 sq. ft.). Includes new raised deck, reroofing of main dwelling and rear garage, and removal of existing brick fireplace.
Permit Issued
Issued on 10/19/2025
Issuing Office
Current Status
Issued on 10/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/9/2025 APPLICANT
Assigned to Plan Check Engineer 8/21/2025 YILE TIAN
Corrections Issued 9/8/2025 YILE TIAN
Quality Review Completed 9/30/2025 KESETE HAREGOT
Plan Check Approved 10/16/2025 YILE TIAN
Issued 10/19/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/3/2025 CINDY QI
Sewer availability Cleared 10/3/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 10/6/2025 CINDY QI
ZI Cleared 10/15/2025 JASON CHAN

Contact Information

Architect Peters,, Douglas Edward; Lic. No.: C30695 3810 WILSHIRE BLVD SUITE 1103      LOS ANGELES, CA 90010
Architect Peters,, Douglas Edward; Lic. No.: NA30695       ,
Contractor Dave C Inc; Lic. No.: 920202-B       ,
Engineer Rooks,, Bret; Lic. No.: C63445 174 LOMA BONITA      SAN LUIS OBISPO, CA 93401
Engineer Rooks,, Bret; Lic. No.: NA63445       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/4/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/8/2025 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/22/2025 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 12/23/2025 Conditional Approval JUAN VALENZUELA
Wood Frame 1/13/2026 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Partial Approval CHRISTOPHE COCHRAN
Insulation 1/14/2026 Partial Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 1/26/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Conditional Approval KEVIN BERBERYAN
Deputy Wood Construction 3/6/2026 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 4/1/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/1/2026 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 4/1/2026 Corrections Issued CHRISTOPHE COCHRAN
Wood Frame 4/1/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/3/2026 Approved CHRISTOPHE COCHRAN
Green Building Rough 4/3/2026 Approved CHRISTOPHE COCHRAN
HVAC-Rough 4/7/2026 Approved CHRISTOPHE COCHRAN
Insulation 4/7/2026 Approved CHRISTOPHE COCHRAN
Service/Power Release 4/7/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 4/16/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/16/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 4/16/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/23/2026 Approved CHRISTOPHE COCHRAN