12318 W STANWOOD DR 90066

Certificate Information: 12318 W STANWOOD DR 90066

Application / Permit
25014-10000-03579
Plan Check / Job No.
B25LA32944
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Garage Conversion ADU with 2 story addition (Total 1,1162 sq.ft) per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 1/29/2026
Issuing Office
Current Status
Issued on 1/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/20/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 JOSEPH RAFOLS
Corrections Issued 10/1/2025 JOSEPH RAFOLS
Quality Review Completed 10/23/2025 HERNAN ARREOLA
Plan Check Approved 1/15/2026 JOSEPH RAFOLS
Issued 1/29/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/4/2025 JESUS LUNA
Roof/Waste drainage to street Cleared 12/4/2025 JESUS LUNA
Specific Plan Cleared 12/9/2025 EDER ROMERO
Eng Process Fee Ord 176,300 Cleared 12/10/2025 JESUS LUNA
Sewer availability Cleared 12/10/2025 JESUS LUNA
GPI Written Notices Cleared 1/15/2026 JOSEPH RAFOLS
Grading Pre-Inspection Cleared 1/15/2026 JOSEPH RAFOLS

Contact Information

Contractor Do Right Construction Co; Lic. No.: 737068-B       ,
Contractor Do Right Management Inc.; Lic. No.: 737068-B       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28531 PALOS VERDES DR EAST      RANCHO PALOS VERDES, CA 90275

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Insulation 7/24/2026   

Inspection Request History

PLUMBING-Rough 3/16/2026 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 3/23/2026 Partial Approval ANTHONY EGSON
Special/Order Compliance 3/23/2026 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 4/21/2026 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Partial Approval RYAN SALAZAR
PLUMBING-Rough 5/18/2026 Partial Approval KIRK SANDERS
Deputy Wood Construction 6/2/2026 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 6/22/2026 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/22/2026 Approved BOBBY KEY
HVAC-Final 6/22/2026 Corrections Issued BOBBY KEY
HVAC-Rough 6/22/2026 Partial Approval BOBBY KEY
PLUMBING-Rough 6/22/2026 Approved BOBBY KEY
BUILDING-Rough-Frame 6/29/2026 Partial Inspection ARAM AVEDISIAN
Final 6/29/2026 Corrections Issued ARAM AVEDISIAN
Insulation 6/29/2026 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 7/22/2026 Conditional Approval KIRK SANDERS
Green Building Rough 7/22/2026 Approved KIRK SANDERS
Insulation 7/22/2026 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 7/22/2026 Conditional Approval KIRK SANDERS
Special/Order Compliance 7/22/2026 Corrections Issued KIRK SANDERS