23906 W HAYNES ST 91307
Certificate Information: 23906 W HAYNES ST 91307
- Application / Permit
- 25014-10000-03578
- Plan Check / Job No.
- B25VN21508
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: GROUND ADDITION TO (E) 1-STORY SFD WITH (E) GARAGE
- Permit Issued
- Issued on 11/13/2025
- Issuing Office
- Current Status
- Issued on 11/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | KHEDER ALRAZAA |
| Corrections Issued | 8/7/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 8/12/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/24/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 11/11/2025 | KHEDER ALRAZAA |
| Issued | 11/13/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/8/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 9/19/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Ha My Design, Inc; Lic. No.: 999603-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/16/2026 | Corrections Issued | TROY SANDERS |
| Wood Frame | 2/24/2026 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 3/24/2026 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Partial Approval | TROY SANDERS |
| Green Building Rough | 3/24/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/7/2026 | Approved | TROY SANDERS |
| HVAC-Rough | 4/7/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/7/2026 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 4/17/2026 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | TROY SANDERS |
| Final | 5/29/2026 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 5/29/2026 | Approved | TROY SANDERS |
| Green Building Final | 5/29/2026 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/29/2026 | Approved | TROY SANDERS |