19632 W HARTLAND ST 91335

Certificate Information: 19632 W HARTLAND ST 91335

Application / Permit
25014-10000-03564
Plan Check / Job No.
B25LA32825
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD. ENLCOSE (E) PATIO COVER AND ADD NEW 8'2" X 5'11" ADDITION TO (E) SFD.
Permit Issued
Issued on 9/25/2025
Issuing Office
Valley
Current Status
CofO Issued on 6/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2025 APPLICANT
Assigned to Plan Check Engineer 8/11/2025 NEHEMIAS RAMOS
Corrections Issued 8/11/2025 NEHEMIAS RAMOS
Building Plans Picked Up 8/14/2025 APPLICANT
Plan Check Approved 8/21/2025 MIROOSH KHACHATOORIAN
Issued 9/25/2025 APPLICANT
CofO in Progress 5/13/2026 ARUTYUN MADATYAN
Permit Finaled 6/24/2026 JOHN JANSON
CofO Issued 6/24/2026 JOHN JANSON
Permit Finaled 6/24/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/20/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/20/2025 RYAN CASTRO

Contact Information

Contractor Active Construction And Design Inc; Lic. No.: 948620-B 18700 SHERMAN WAY # 210      RESEDA, CA 91335
Engineer Mobed,, Ashkan; Lic. No.: C92493 23450 KITTREDGE ST      WEST HILLS, CA 91307

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/20/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 10/22/2025 Partial Approval ARUTYUN MADATYAN
Deputy Drilled-In Anchors 10/30/2025 Conditional Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 11/6/2025 Approved ARUTYUN MADATYAN
Deputy Drilled-In Anchors 12/4/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 12/12/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 12/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 12/12/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 1/14/2026 Approved KRISTEN CAUSEY
HVAC-Rough 1/14/2026 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/14/2026 Partial Approval KRISTEN CAUSEY
PLUMBING-Rough 1/14/2026 Approved KRISTEN CAUSEY
Insulation 1/29/2026 Approved ARUTYUN MADATYAN
Drywall Nailing 2/10/2026 Approved ARUTYUN MADATYAN
Shower Pan 2/10/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/13/2026 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/24/2026 Approved JUAN ALVARADO
Final 4/24/2026 Corrections Issued JUAN ALVARADO
Green Building Final 4/24/2026 Not Ready for Inspection JUAN ALVARADO
Green Building Rough 4/24/2026 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Approved JUAN ALVARADO
Smoke Detectors 4/24/2026 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Final 5/12/2026 Approved ARUTYUN MADATYAN
Final 5/12/2026 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 5/12/2026 Approved ARUTYUN MADATYAN
HVAC-Final 5/12/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 5/12/2026 Approved ARUTYUN MADATYAN
Service/Power Release 5/12/2026 Approved ARUTYUN MADATYAN
Smoke Detectors 5/12/2026 Approved ARUTYUN MADATYAN