19632 W HARTLAND ST 91335
Certificate Information: 19632 W HARTLAND ST 91335
- Application / Permit
- 25014-10000-03564
- Plan Check / Job No.
- B25LA32825
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD. ENLCOSE (E) PATIO COVER AND ADD NEW 8'2" X 5'11" ADDITION TO (E) SFD.
- Permit Issued
- Issued on 9/25/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 8/11/2025 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 8/14/2025 | APPLICANT |
| Plan Check Approved | 8/21/2025 | MIROOSH KHACHATOORIAN |
| Issued | 9/25/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 6/24/2026 | JOHN JANSON |
| CofO Issued | 6/24/2026 | JOHN JANSON |
| Permit Finaled | 6/24/2026 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/20/2025 | RYAN CASTRO |
Contact Information
| Contractor | Active Construction And Design Inc; Lic. No.: 948620-B | 18700 SHERMAN WAY # 210 RESEDA, CA 91335 |
| Engineer | Mobed,, Ashkan; Lic. No.: C92493 | 23450 KITTREDGE ST WEST HILLS, CA 91307 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/20/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/22/2025 | Partial Approval | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 10/30/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 11/6/2025 | Approved | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 12/4/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/12/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 12/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 1/14/2026 | Approved | KRISTEN CAUSEY |
| HVAC-Rough | 1/14/2026 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/14/2026 | Partial Approval | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/14/2026 | Approved | KRISTEN CAUSEY |
| Insulation | 1/29/2026 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 2/10/2026 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 2/10/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 4/24/2026 | Approved | JUAN ALVARADO |
| Final | 4/24/2026 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 4/24/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 4/24/2026 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 4/24/2026 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/12/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 5/12/2026 | Approved | ARUTYUN MADATYAN |