756 W 123RD ST 90044

Certificate Information: 756 W 123RD ST 90044

Application / Permit
25014-10000-03474
Plan Check / Job No.
B25LA31878
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 12'-3" X 18'-6" ROOM ADDITION AT REAR OF (E) SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 11/25/2025
Issuing Office
Metro
Current Status
Issued on 11/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2025 APPLICANT
Assigned to Plan Check Engineer 8/4/2025 LAWRENCE QUIRANTE
Corrections Issued 8/6/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 8/8/2025 APPLICANT
Applicant returned to address corrections 11/6/2025 AUNG SOE
Plan Check Approved 11/25/2025 JONATHAN PLATERO
Issued 11/25/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/24/2025 JEFF LOREDO
Roof/Waste drainage to street Cleared 11/24/2025 JEFF LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/15/2026 Conditional Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 1/15/2026 Approved BEN MOLSTAD
Footing/Foundation/Slab 1/15/2026 Approved BEN MOLSTAD
METHANE-Barrier 1/15/2026 Approved BEN MOLSTAD
METHANE-Subgrade 1/15/2026 Approved BEN MOLSTAD
BUILDING-Rough-Frame 2/4/2026 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 2/4/2026 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Corrections Issued BEN MOLSTAD
Green Building Rough 2/4/2026 Not Ready for Inspection BEN MOLSTAD
METHANE-Rough 2/4/2026 Approved BEN MOLSTAD
Wood Frame 2/4/2026 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 2/6/2026 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Partial Approval BEN MOLSTAD
Wood Frame 2/6/2026 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/18/2026 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Approved JOSEPH MCGARRY
Green Building Rough 2/18/2026 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 2/18/2026 Approved JOSEPH MCGARRY
Insulation 2/24/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 2/24/2026 Approved ARTHUR NEGRETE
Drywall Nailing 3/2/2026 Approved BEN MOLSTAD
BUILDING-Rough-Frame 4/22/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 4/22/2026 Approved ARTHUR NEGRETE
Final 4/22/2026 Corrections Issued JOSEPH MCGARRY
Green Building Final 4/22/2026 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Not Ready ARTHUR NEGRETE
Smoke Detectors 4/22/2026 Corrections Issued ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Not Ready BEN MOLSTAD
Final 5/11/2026 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Approved BEN MOLSTAD
Smoke Detectors 5/11/2026 Not Ready for Inspection BEN MOLSTAD
Final 5/13/2026 Corrections Issued BEN MOLSTAD
Smoke Detectors 5/13/2026 Approved BEN MOLSTAD