2029 N HYPERION AVE 90027
Certificate Information: 2029 N HYPERION AVE 90027
- Application / Permit
- 25014-10000-03453
- Plan Check / Job No.
- B25LA31680
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Addition and Remodel to existing Single-Family Dwelling. Type VB construction. Work per soils report.
- Permit Issued
- Issued on 12/8/2025
- Issuing Office
- Current Status
- Issued on 12/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | ALEXIS VERDUGO |
| Corrections Issued | 8/18/2025 | ALEXIS VERDUGO |
| Quality Review Completed | 9/5/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/8/2025 | ALEXIS VERDUGO |
| Applicant returned to address corrections | 11/5/2025 | ALEXIS VERDUGO |
| Applicant returned to address corrections | 11/6/2025 | ALEXIS VERDUGO |
| Plan Check Approved | 11/19/2025 | ALEXIS VERDUGO |
| Issued | 12/8/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/16/2025 | ROSALINDA MEZA |
| ZI | Cleared | 9/16/2025 | ROSALINDA MEZA |
| BHO/Hillside ordinance | Cleared | 9/25/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/25/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/25/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/25/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/25/2025 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 9/26/2025 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 9/30/2025 | JEANIE LAM |
| GPI Written Notices | Cleared | 11/6/2025 | ALEXIS VERDUGO |
| Grading Pre-Inspection | Cleared | 11/6/2025 | ALEXIS VERDUGO |
Contact Information
| Architect | Anderson,, Anthony Ryan; Lic. No.: C31522 | 1940 PALMER AVENUE #3013 LARCHMONT, NY 10538 |
| Contractor | Best Bet Builders; Lic. No.: 1110108-B | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Shower Pan | 6/8/2026 |
| Insulation | 6/8/2026 |
Inspection Request History
| Pre-Inspection | 1/6/2026 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 2/20/2026 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/25/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/25/2026 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/2/2026 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/2/2026 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/10/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/27/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 3/27/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 3/27/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/27/2026 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 3/27/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/8/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/8/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/8/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 4/23/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/23/2026 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/13/2026 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 5/13/2026 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/20/2026 | Approved | ENRIQUE MIRELES |
| Insulation | 5/20/2026 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 5/20/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/28/2026 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/28/2026 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/28/2026 | Approved | ENRIQUE MIRELES |