2207 S THURMAN AVE 90016

Certificate Information: 2207 S THURMAN AVE 90016

Application / Permit
25014-10000-03389
Plan Check / Job No.
B25LA30979
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] 2-story additional/remodel to (E) 1-story SFD. New rooftop deck with trellis.
Permit Issued
Issued on 1/2/2026
Issuing Office
Current Status
Issued on 1/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 JOSEPH RAFOLS
Corrections Issued 8/12/2025 JOSEPH RAFOLS
Quality Review Completed 8/22/2025 HERNAN ARREOLA
Plan Check Approved 11/19/2025 JOSEPH RAFOLS
Issued 1/2/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/2/2025 CELINA MORENO
Sewer availability Cleared 9/2/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/3/2025 CELINA MORENO

Contact Information

Contractor Bela Remodeling; Lic. No.: 1038287-B       ,
Engineer Salem,, Yasser; Lic. No.: NA4902       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/11/2026 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 2/13/2026 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 2/13/2026 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 3/4/2026 Not Ready for Inspection BRENDAN MORELLI
Deputy Drilled-In Anchors 3/4/2026 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 3/4/2026 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 3/4/2026 Not Ready for Inspection BRENDAN MORELLI
Insulation 3/4/2026 Not Ready for Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 3/6/2026 Approved WILLIAM SIERRA
Insulation 3/6/2026 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval BRENDAN MORELLI
Special/Order Compliance 3/26/2026 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 3/27/2026 Partial Inspection BRENDAN MORELLI
Footing/Foundation/Slab 4/21/2026 No Access for Inspection WILLIAM SIERRA
Footing/Foundation/Slab 4/24/2026 Approved WILLIAM SIERRA
Deck 5/13/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/13/2026 Partial Approval DAVID WILLIAMS
PLUMBING-Rough 6/2/2026 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Rough 7/2/2026 Approved RONNIE MINDANAO
HVAC-Rough 7/2/2026 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 7/2/2026 Approved RONNIE MINDANAO
Wood Frame 7/2/2026 Order to Comply Issued RONNIE MINDANAO
BUILDING-Rough-Frame 7/7/2026 Not Ready for Inspection DAVID WILLIAMS
Deputy Wood Construction 7/7/2026 Conditional Approval DAVID WILLIAMS
Green Building Rough 7/7/2026 Approved DAVID WILLIAMS
HVAC-Rough 7/7/2026 Corrections Issued DAVID WILLIAMS
Wood Frame 7/7/2026 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 7/10/2026 Not Ready for Inspection DAVID WILLIAMS
HVAC-Rough 7/10/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 7/14/2026 Partial Approval DAVID WILLIAMS
Shower Pan 7/14/2026 Approved DAVID WILLIAMS