1738 W 38TH PL 90062
Certificate Information: 1738 W 38TH PL 90062
- Application / Permit
- 25014-10000-03373
- Plan Check / Job No.
- B25LA30886
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AT REAR OF (E) 1-STORY SFD
- Permit Issued
- Issued on 9/2/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2025 | SAMUEL GONZALEZ |
| Corrections Issued | 7/30/2025 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 8/5/2025 | APPLICANT |
| Plan Check Approved | 8/22/2025 | MINA HABILI |
| Issued | 9/2/2025 | APPLICANT |
| CofO in Progress | 6/1/2026 | SABAS ALONSO |
| CofO Issued | 6/2/2026 | DEROLD HAUFF |
| Permit Finaled | 6/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/14/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vo,, Tung Thanh; Lic. No.: C69546 | 11122 BIXLER CIRCLE GARDEN GROVE, CA 92840 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 11/13/2025 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 1/12/2026 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 2/5/2026 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 2/5/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/5/2026 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/5/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/11/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 2/11/2026 | Approved | SABAS ALONSO |
| Insulation | 2/13/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 2/27/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/5/2026 | Approved | GEM DE OCAMPO |
| Shower Pan | 3/5/2026 | Approved | GEM DE OCAMPO |
| Final | 5/1/2026 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 5/1/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/1/2026 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 5/1/2026 | Approved | SABAS ALONSO |
| Final | 5/29/2026 | OK to Issue CofO | SABAS ALONSO |