2725-2727 S MIDVALE AVE 90064

Certificate Information: 2725-2727 S MIDVALE AVE 90064

Application / Permit
25014-10000-03356
Plan Check / Job No.
B25LA30682
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING ADDITION TO CONVERT PORTION OF SFD INTO AN ATTACHED ADU PER ORDINANCE LAMC 12.22 A.33 (c) and (e) NFPA13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 11/26/2025
Issuing Office
Current Status
Issued on 11/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 ZENA HADDIS
Corrections Issued 8/1/2025 JAD BASMA
Quality Review Completed 8/8/2025 PRANITA SHAH
Plan Check Approved 11/26/2025 ZENA HADDIS
Issued 11/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/6/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/7/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/7/2025 DAVID LOPEZ
Sewer availability Cleared 8/7/2025 DAVID LOPEZ
Specific Plan Cleared 8/19/2025 YINGSHI HUANG
Specific Plan Cleared 8/22/2025 PEDRO AYALA
Hydrant and Access approval Cleared 8/27/2025 RUEL COLE
Construction near power lines Cleared 11/19/2025 EDGAR PASCUA
Flood clearance Cleared 11/19/2025 ELYSE GREPO
GPI Written Notices Cleared 11/20/2025 JAD BASMA
Grading Pre-Inspection Cleared 11/20/2025 JAD BASMA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Value Up Renovation & Construction; Lic. No.: 1031128-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/29/2025 Approved KIRK SANDERS
Footing/Foundation/Slab 12/29/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 1/14/2026 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 1/14/2026 Partial Approval ARAM AVEDISIAN
Sewer 1/14/2026 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
FLOOD-Proofing Certificate 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
Green Building Rough 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
MERV13>=Rough 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Corrections Issued DANIEL VERA
Wood Frame 1/21/2026 Partial Inspection DANIEL VERA
FLOOD-Proofing Certificate 3/3/2026 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Approved ARAM AVEDISIAN
HVAC-Rough 3/16/2026 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 3/16/2026 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 3/26/2026 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Rough 3/26/2026 Approved MICHAEL ALLEN
Green Building Rough 3/26/2026 Approved MICHAEL ALLEN
HVAC-Rough 3/26/2026 Approved MICHAEL ALLEN
Insulation 3/26/2026 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 3/26/2026 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 3/26/2026 Approved MICHAEL ALLEN
Drywall Nailing 4/3/2026 Approved RYAN SALAZAR
Insulation 4/3/2026 Approved RYAN SALAZAR
Shower Pan 4/3/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/13/2026 Approved WILBER ROSALES