2725-2727 S MIDVALE AVE 90064
Certificate Information: 2725-2727 S MIDVALE AVE 90064
- Application / Permit
- 25014-10000-03356
- Plan Check / Job No.
- B25LA30682
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING ADDITION TO CONVERT PORTION OF SFD INTO AN ATTACHED ADU PER ORDINANCE LAMC 12.22 A.33 (c) and (e) NFPA13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 11/26/2025
- Issuing Office
- Current Status
- Issued on 11/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | ZENA HADDIS |
| Corrections Issued | 8/1/2025 | JAD BASMA |
| Quality Review Completed | 8/8/2025 | PRANITA SHAH |
| Plan Check Approved | 11/26/2025 | ZENA HADDIS |
| Issued | 11/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/7/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/7/2025 | DAVID LOPEZ |
| Specific Plan | Cleared | 8/19/2025 | YINGSHI HUANG |
| Specific Plan | Cleared | 8/22/2025 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 8/27/2025 | RUEL COLE |
| Construction near power lines | Cleared | 11/19/2025 | EDGAR PASCUA |
| Flood clearance | Cleared | 11/19/2025 | ELYSE GREPO |
| GPI Written Notices | Cleared | 11/20/2025 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 11/20/2025 | JAD BASMA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Value Up Renovation & Construction; Lic. No.: 1031128-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/29/2025 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 12/29/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/14/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/14/2026 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 1/14/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| FLOOD-Proofing Certificate | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| MERV13>=Rough | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Corrections Issued | DANIEL VERA |
| Wood Frame | 1/21/2026 | Partial Inspection | DANIEL VERA |
| FLOOD-Proofing Certificate | 3/3/2026 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/16/2026 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/16/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/26/2026 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/26/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 3/26/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 3/26/2026 | Approved | MICHAEL ALLEN |
| Insulation | 3/26/2026 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 3/26/2026 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 3/26/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/3/2026 | Approved | RYAN SALAZAR |
| Insulation | 4/3/2026 | Approved | RYAN SALAZAR |
| Shower Pan | 4/3/2026 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/13/2026 | Approved | WILBER ROSALES |