1339-1341 N MILLER DR 90069

Certificate Information: 1339-1341 N MILLER DR 90069

Application / Permit
25014-10000-03330
Plan Check / Job No.
B25LA30504
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Convert portion of the single family dwelling to new junior accessory dwelling unit PER GC 66323(a)(1) and 66333 . All work per engineering "COMPLY WITH DEPARTMENT ORDER effective date 09/15/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/12/2025
Issuing Office
Current Status
CofO Issued on 6/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2025 APPLICANT
Assigned to Plan Check Engineer 7/25/2025 NAREG ATARIAN
Corrections Issued 7/25/2025 NAREG ATARIAN
Applicant returned to address corrections 9/17/2025 NAREG ATARIAN
Applicant returned to address corrections 9/24/2025 SARKIS HARABEDIAN
Plan Check Approved 10/9/2025 ARAMIK SHAHMIRZAIAN
Issued 10/12/2025 APPLICANT
CofO in Progress 4/3/2026 PTOLEMY HILL
Permit Finaled 6/22/2026 DANIEL SANCHEZ
CofO Issued 6/22/2026 DANIEL SANCHEZ
Permit Finaled 6/22/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 7/29/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/29/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/29/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Fisher,, Mark; Lic. No.: C56341 333 ORANGE AVE UNIT 4      CORONADO, CA 92118

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2025 No Access for Inspection PTOLEMY HILL
Pre-Inspection 12/2/2025 Approved PTOLEMY HILL
BUILDING-Rough-Frame 2/18/2026 Approved PTOLEMY HILL
Final 2/18/2026 Corrections Issued PTOLEMY HILL
Green Building Final 2/18/2026 Not Ready for Inspection PTOLEMY HILL
Green Building Rough 2/18/2026 Approved PTOLEMY HILL
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved PTOLEMY HILL
Smoke Detectors 2/18/2026 Approved PTOLEMY HILL
Final 4/3/2026 OK to Issue CofO PTOLEMY HILL
Green Building Final 4/3/2026 Approved PTOLEMY HILL