17600 W RUNNYMEDE ST 91406

Certificate Information: 17600 W RUNNYMEDE ST 91406

Application / Permit
25014-10000-03301
Plan Check / Job No.
B25LA30130
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition and remodel to existing 1 story single family dewlling with attached garage per engineer design
Permit Issued
Issued on 8/11/2025
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2025 APPLICANT
Assigned to Plan Check Engineer 7/25/2025 AUNG SOE
Corrections Issued 7/29/2025 AUNG SOE
Building Plans Picked Up 7/29/2025 APPLICANT
Plan Check Approved 8/11/2025 JOHN MESIAS
Issued 8/11/2025 APPLICANT
CofO in Progress 2/4/2026 GAREN HAYRAPETYAN
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/28/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/28/2025 MICHAEL BROWN
Sewer availability Cleared 7/28/2025 MICHAEL BROWN

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/13/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 8/13/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 8/13/2025 Not Ready for Inspection SALVADOR MARTINEZ
Deputy Drilled-In Anchors 8/18/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 8/21/2025 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/21/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/1/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 10/1/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 10/1/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 10/1/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/7/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 10/7/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 10/7/2025 Approved GAREN HAYRAPETYAN
Shower Pan 10/7/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/10/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 10/10/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/10/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/16/2025 Approved WAYNE REGESTER
Insulation 10/22/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 10/24/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 10/24/2025 Not Ready for Inspection WAYNE REGESTER
Final 1/21/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/21/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/21/2026 Approved JENNIFER RABUCHIN
Final 2/2/2026 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 2/2/2026 Approved GAREN HAYRAPETYAN