18068 W BLUE SAIL DR 90272
Certificate Information: 18068 W BLUE SAIL DR 90272
- Application / Permit
- 25014-10000-03293
- Plan Check / Job No.
- B25LA30000
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **2025 EO8 ELIGIBLEWILDFIRE PROJECT** NEW 2ND FLOOR ADDITION TO (E) SFD. MAINTAIN PORTION OF EXISTING BLDG
- Permit Issued
- Issued on 11/10/2025
- Issuing Office
- Current Status
- Issued on 11/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | MANUEL MONTUFAR |
| Corrections Issued | 7/28/2025 | MANUEL MONTUFAR |
| Quality Review Completed | 7/28/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/3/2025 | MANUEL MONTUFAR |
| Plan Check Approved | 11/7/2025 | MANUEL MONTUFAR |
| Issued | 11/10/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 7/28/2025 | JESSICA OPINION |
| ZA Case | Cleared | 10/7/2025 | BRENNEN OBETO |
| ZA Case | Cleared | 10/7/2025 | BRENNEN OBETO |
| Miscellaneous | Cleared | 10/22/2025 | KENTON TRINH |
| Miscellaneous | Cleared | 10/22/2025 | KENTON TRINH |
| Coastal Zone | Cleared | 10/28/2025 | NOAH MCCOY |
Contact Information
| Contractor | Dean Farrar Construction Inc; Lic. No.: 917442-B | , |
| Contractor | Farrar Dean Construction Inc; Lic. No.: 917442-B | , |
| Engineer | Shirley,, Peter; Lic. No.: NA75050 | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/3/2025 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/10/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/20/2026 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | DANIEL VERA |
| Green Building Rough | 1/26/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Partial Approval | DANIEL VERA |
| Green Building Rough | 4/6/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Partial Approval | DANIEL VERA |
| Green Building Rough | 4/21/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2026 | Approved | DANIEL VERA |
| Green Building Rough | 7/6/2026 | Not Ready for Inspection | DANIEL VERA |