8010 S YORKTOWN AVE 90045

Certificate Information: 8010 S YORKTOWN AVE 90045

Application / Permit
25014-10000-03261
Plan Check / Job No.
B25LA29803
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW STORAGE BUILDING ATTACHED TO EXISTING GARAGE IN REAR OF LOT
Permit Issued
Issued on 12/12/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2025 APPLICANT
Assigned to Plan Check Engineer 7/23/2025 NEHEMIAS RAMOS
Corrections Issued 7/23/2025 NEHEMIAS RAMOS
Building Plans Picked Up 8/1/2025 APPLICANT
Applicant returned to address corrections 11/19/2025 BEHROUZ KHOKHAR
Plan Check Approved 11/21/2025 BEHROUZ KHOKHAR
Issued 12/12/2025 APPLICANT
CofO in Progress 5/15/2026 MICHAEL LEWIS
Permit Finaled 5/19/2026 RICHARD STEINBACH
CofO Issued 5/19/2026 RICHARD STEINBACH
Permit Finaled 5/19/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/6/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 9/10/2025 JESUS CISNEROS
Construction near power lines Cleared 10/2/2025 RIDWAN HARDY
Construction within easement Cleared 10/2/2025 RIDWAN HARDY

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Botanica Landscape Inc; Lic. No.: 711054-B 6237 WEST 83RD PLACE      LOS ANGELES, CA 90045

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2026 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/20/2026 Approved MICHAEL ALLEN
Footing/Foundation/Slab 2/20/2026 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 3/20/2026 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 3/20/2026 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Partial Approval ANTHONY EGSON
Green Building Rough 3/20/2026 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 3/24/2026 Conditional Approval JESUS PINEDA
ELECTRICAL-Rough 3/24/2026 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 4/1/2026 Approved JESUS PINEDA
Insulation 4/8/2026 Approved EUGENE CASSIDY
Drywall Nailing 4/13/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/8/2026 Approved JESUS PINEDA
ELECTRICAL-Final 5/8/2026 Approved JESUS PINEDA
Final 5/8/2026 Corrections Issued JESUS PINEDA
Green Building Final 5/8/2026 Approved JESUS PINEDA
Green Building Rough 5/8/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved JESUS PINEDA
Smoke Detectors 5/8/2026 Approved JESUS PINEDA
Final 5/14/2026 OK to Issue CofO MICHAEL LEWIS
Special/Order Compliance 5/14/2026 Approved MICHAEL LEWIS