8010 S YORKTOWN AVE 90045
Certificate Information: 8010 S YORKTOWN AVE 90045
- Application / Permit
- 25014-10000-03261
- Plan Check / Job No.
- B25LA29803
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW STORAGE BUILDING ATTACHED TO EXISTING GARAGE IN REAR OF LOT
- Permit Issued
- Issued on 12/12/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 7/23/2025 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 8/1/2025 | APPLICANT |
| Applicant returned to address corrections | 11/19/2025 | BEHROUZ KHOKHAR |
| Plan Check Approved | 11/21/2025 | BEHROUZ KHOKHAR |
| Issued | 12/12/2025 | APPLICANT |
| CofO in Progress | 5/15/2026 | MICHAEL LEWIS |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
| CofO Issued | 5/19/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/6/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2025 | JESUS CISNEROS |
| Construction near power lines | Cleared | 10/2/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/2/2025 | RIDWAN HARDY |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Botanica Landscape Inc; Lic. No.: 711054-B | 6237 WEST 83RD PLACE LOS ANGELES, CA 90045 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/18/2026 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 2/20/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/20/2026 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 3/20/2026 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 3/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/24/2026 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 3/24/2026 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/1/2026 | Approved | JESUS PINEDA |
| Insulation | 4/8/2026 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/13/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 5/8/2026 | Approved | JESUS PINEDA |
| Final | 5/8/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 5/8/2026 | Approved | JESUS PINEDA |
| Green Building Rough | 5/8/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 5/8/2026 | Approved | JESUS PINEDA |
| Final | 5/14/2026 | OK to Issue CofO | MICHAEL LEWIS |
| Special/Order Compliance | 5/14/2026 | Approved | MICHAEL LEWIS |