10320 S ST ANDREWS PL 90047
Certificate Information: 10320 S ST ANDREWS PL 90047
- Application / Permit
- 25014-10000-03215
- Plan Check / Job No.
- B25LA29360
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) DET GARAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2).
- Permit Issued
- Issued on 11/13/2025
- Issuing Office
- Current Status
- Issued on 11/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2025 | KAMYAR EMAMI |
| Corrections Issued | 7/19/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 11/3/2025 | KAMYAR EMAMI |
| Plan Check Approved | 11/9/2025 | ISIS ARGUETA |
| Issued | 11/13/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 9/5/2025 | FIPE LEILUA |
| Address approval | Cleared | 9/6/2025 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 9/6/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | ERIK BEASLEY |
| Construction near power lines | Cleared | 9/26/2025 | RIDWAN HARDY |
| Sewer availability | Cleared | 10/30/2025 | ERIK BEASLEY |
Contact Information
| Contractor | B & W Holdings Inc; Lic. No.: 968742-B | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/9/2026 | Partial Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 3/6/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 4/1/2026 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 4/6/2026 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/10/2026 | Corrections Issued | SALVADOR MARTINEZ |
| METHANE-Barrier | 4/10/2026 | Approved | SALVADOR MARTINEZ |
| METHANE-Subgrade | 4/10/2026 | Approved | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 4/15/2026 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 4/15/2026 | Approved | SALVADOR MARTINEZ |