2224 N RIVERDALE AVE 90031
Certificate Information: 2224 N RIVERDALE AVE 90031
- Application / Permit
- 25014-10000-03204
- Plan Check / Job No.
- B25LA29211
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSURE EXISING COVERD PORCH REMOVE EXISTING PORCH'S ROOF FRAMING AND EXTEND MAIN ROOF'S RIDGE, CREATE AN EXIT DOOR AT BEDROOM #4 IN EXISTING SFD WITH BASEMENT
- Permit Issued
- Issued on 8/15/2025
- Issuing Office
- Current Status
- Permit Finaled on 11/4/2025
Permit Application Status History
| Submitted | 7/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | JOE VO |
| Plan Check Approved | 7/22/2025 | JOE VO |
| Issued | 8/15/2025 | APPLICANT |
| Permit Finaled | 11/3/2025 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Cali Luxury Builders Inc; Lic. No.: 1127045-B | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: NA43117 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2025 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 9/8/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/26/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/3/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/3/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/3/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/7/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/7/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/17/2025 | Approved | DEVON JACKSON |
| Final | 11/3/2025 | Permit Finaled | HAMIK HARTOUNIAN |
| MERV13>=Final | 11/3/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/3/2025 | Approved | HAMIK HARTOUNIAN |