7333 N MCLAREN AVE 91307
Certificate Information: 7333 N MCLAREN AVE 91307
- Application / Permit
- 25014-10000-03175
- Plan Check / Job No.
- B25LA28986
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR OF (E) SFD WITH ATTACHED GARAGE. CONST. PER W.F.P.P.
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 7/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/19/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/22/2025 | APPLICANT |
| Applicant returned to address corrections | 8/12/2025 | SHANGQIN XIE |
| Plan Check Approved | 8/13/2025 | CARLOS MONTES |
| Issued | 8/20/2025 | APPLICANT |
| CofO in Progress | 7/13/2026 | JEFFREY HARTLINE |
| No Progress | 7/15/2026 | JEFFREY HARTLINE |
| CofO in Progress | 7/15/2026 | JEFFREY HARTLINE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/12/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/22/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 9/10/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Pre-Inspection | 9/11/2025 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 9/23/2025 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/20/2025 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 12/12/2025 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 12/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Not Ready | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 6/4/2026 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 6/4/2026 | Approved | JEFFREY HARTLINE |
| Final | 6/4/2026 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 6/4/2026 | Approved | JEFFREY HARTLINE |
| Green Building Final | 6/4/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 6/4/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 6/4/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 6/4/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 6/4/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 6/4/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 6/15/2026 | Approved | JEFFREY HARTLINE |
| Final | 6/15/2026 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Final | 6/15/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 6/15/2026 | Approved | JEFFREY HARTLINE |
| Smoke Detectors | 6/15/2026 | Approved | JEFFREY HARTLINE |
| Final | 7/10/2026 | OK to Issue CofO | JEFFREY HARTLINE |