7003 S 5TH AVE 90043
Certificate Information: 7003 S 5TH AVE 90043
- Application / Permit
- 25014-10000-03145
- Plan Check / Job No.
- B25LA28781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DTEACHED GARAGE, STORAGE ROOM, WITH ADDITION TO BECOME A DETACHED ACCSESORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/20/2025
- Issuing Office
- Current Status
- CofO Issued on 3/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2025 | JOSE VELAZQUEZ |
| Corrections Issued | 7/17/2025 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 9/12/2025 | JOSE VELAZQUEZ |
| Plan Check Approved | 9/17/2025 | DANIEL YIP |
| Issued | 9/20/2025 | APPLICANT |
| CofO in Progress | 3/13/2026 | SALVADOR MARTINEZ |
| Permit Finaled | 3/15/2026 | DEROLD HAUFF |
| CofO Issued | 3/15/2026 | DEROLD HAUFF |
| Permit Finaled | 3/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 7/24/2025 | DERRICK MAGEE |
| Construction near power lines | Cleared | 9/8/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 9/9/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 11/3/2025 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 11/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/5/2025 | Partial Approval | SALVADOR MARTINEZ |
| Underground Mechanical | 11/5/2025 | Partial Approval | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/21/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 11/21/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/25/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 11/25/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Conditional Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/26/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/31/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/31/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/2/2026 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 1/2/2026 | Approved | WILLIAM SIERRA |
| Footing/Foundation/Slab | 1/2/2026 | Approved | WILLIAM SIERRA |
| Green Building Rough | 1/2/2026 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 1/2/2026 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 1/2/2026 | Partial Approval | WILLIAM SIERRA |
| Insulation | 1/12/2026 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 1/15/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 1/27/2026 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 2/13/2026 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 2/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 2/27/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 2/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 2/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV No Gas | SALVADOR MARTINEZ |
| Smoke Detectors | 2/27/2026 | Approved | SALVADOR MARTINEZ |
| Final | 3/9/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 3/9/2026 | Approved | SALVADOR MARTINEZ |
| Final | 3/11/2026 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 3/11/2026 | Approved | SALVADOR MARTINEZ |