3028 S 12TH AVE 90018
Certificate Information: 3028 S 12TH AVE 90018
- Application / Permit
- 25014-10000-03053
- Plan Check / Job No.
- B25LA27855
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Remodel and rear addition to existing S.F.D.
- Permit Issued
- Issued on 9/15/2025
- Issuing Office
- Current Status
- CofO in Progress on 3/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2025 | CAROLEAN BASMA |
| Corrections Issued | 7/15/2025 | CAROLEAN BASMA |
| Plan Check Approved | 8/1/2025 | CAROLEAN BASMA |
| Issued | 9/15/2025 | APPLICANT |
| CofO in Progress | 3/26/2026 | JUSTIN HAWLEY |
| CofO in Progress | 3/27/2026 | JUSTIN HAWLEY |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/21/2025 | CINDY QI |
| Sewer availability | Cleared | 7/21/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2025 | CINDY QI |
Contact Information
| Contractor | Gwn Construction Llc; Lic. No.: 1072282-B | , |
| Contractor | Neilan Grant Wayne; Lic. No.: 1072282-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/25/2025 | Approved | ALEX COLIN |
| Underground Mechanical | 9/25/2025 | Approved | ALEX COLIN |
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Conditional Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 10/1/2025 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/9/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/6/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | JUSTIN HAWLEY |
| Gas Test | 11/25/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/25/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 11/25/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 12/5/2025 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 12/18/2025 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/18/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 3/19/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/19/2026 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/19/2026 | Approved | JUSTIN HAWLEY |
| Gas Test | 3/19/2026 | Approved | JUSTIN HAWLEY |
| Green Building Final | 3/19/2026 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/19/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/19/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 3/19/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/26/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 3/26/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/26/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 5/15/2026 | Corrections Issued | JUSTIN HAWLEY |