1012 E INDIANA AVE 90291
Certificate Information: 1012 E INDIANA AVE 90291
- Application / Permit
- 25014-10000-03023
- Plan Check / Job No.
- B25LA27654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1) Major remodel and addition to (e) 1 story SFD. To be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 2/15/2026
- Issuing Office
- Current Status
- Issued on 2/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 7/24/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/1/2025 | TU HUA |
| Applicant returned to address corrections | 11/18/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 2/13/2026 | MARCELA FRANQUEZ |
| Issued | 2/15/2026 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 8/13/2025 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/15/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 10/1/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/1/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 10/2/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/2/2025 | RIDWAN HARDY |
| Specific Plan | Cleared | 10/10/2025 | EDER ROMERO |
Contact Information
| Architect | Contento,, Lindsey Sherman; Lic. No.: NA36546 | , |
| Contractor | Progressive Construction Inc; Lic. No.: 1024265-B | , |
| Contractor | Progressive Design & Build; Lic. No.: 1024265-B | , |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/9/2026 |
| PLUMBING-Rough | 6/9/2026 |
| Green Building Rough | 6/9/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 4/9/2026 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 4/14/2026 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 4/14/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 4/17/2026 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 4/23/2026 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2026 | Partial Approval | RUBEN RIVAS |