4662 N VERDUGO ROAD 90065

Certificate Information: 4662 N VERDUGO ROAD 90065

Application / Permit
25014-10000-03022
Plan Check / Job No.
B25LA27649
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT 655 SF PORTION OF (E) DETACHED GARAGE + 149 SF ADDITION INTO AN ADU PER LAMC12.22A.33(b)(1)3. CONVERT REMAINING 60 SF PORTION OF EXISTING DETACHED GARAGE INTO A (N) LAUNDRY ROOM. ALL WORK PER ENG.
Permit Issued
Issued on 8/15/2025
Issuing Office
Current Status
CofO Issued on 7/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2025 APPLICANT
Assigned to Plan Check Engineer 7/7/2025 LUISANGEL VALENZUELA
Corrections Issued 7/8/2025 LUISANGEL VALENZUELA
Plan Check Approved 8/7/2025 LUISANGEL VALENZUELA
No Progress 8/15/2025 LUISANGEL VALENZUELA
Plan Check Approved 8/15/2025 LUISANGEL VALENZUELA
Issued 8/15/2025 APPLICANT
CofO in Progress 7/7/2026 RONNIE MEDINA
Permit Finaled 7/8/2026 DEROLD HAUFF
CofO Issued 7/8/2026 DEROLD HAUFF
Permit Finaled 7/8/2026 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/11/2025 RAMAZANALI ALMASI
Address approval Cleared 7/18/2025 DAVID LOPEZ
Construction near power lines Cleared 7/18/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/18/2025 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 7/18/2025 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 7/18/2025 VLADIMIR ARUTYUNYAN
Tenant Habitability Plan Cleared 7/23/2025 KORNEL LELEA
Supp. Use District POD/CDO/TDO Cleared 7/31/2025 ANDREA MAGANA-WITHERS
ZI Cleared 7/31/2025 ANDREA MAGANA-WITHERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/2/2025 Approved RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 12/4/2025 Not Ready for Inspection RONNIE MEDINA
Pre-Inspection 12/4/2025 Not Ready for Inspection RONNIE MEDINA
Footing/Foundation/Slab 12/30/2025 Partial Approval RONNIE MEDINA
Special/Order Compliance 1/20/2026 Corrections Issued GEM DE OCAMPO
Footing/Foundation/Slab 1/29/2026 Approved RONNIE MEDINA
Deputy Wood Construction 3/23/2026 Conditional Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Corrections Issued RONNIE MEDINA
Green Building Rough 3/31/2026 Not Ready for Inspection RONNIE MEDINA
Interior/Exterior Lathing 3/31/2026 Corrections Issued RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Not Ready RONNIE MEDINA
Smoke Detectors 3/31/2026 Not Ready for Inspection RONNIE MEDINA
Wood Frame 3/31/2026 Corrections Issued RONNIE MEDINA
Insulation 4/3/2026 Partial Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Approved RONNIE MEDINA
Green Building Rough 4/9/2026 Approved RONNIE MEDINA
Verify Sprinkler Sign Off 4/9/2026 Approved RONNIE MEDINA
Wood Frame 4/9/2026 Approved RONNIE MEDINA
Insulation 4/13/2026 Approved DAVID WILLIAMS
Drywall Nailing 4/16/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 4/27/2026 Approved RONNIE MEDINA
Pre-Inspection 5/15/2026 Corrections Issued RONNIE MEDINA
Special/Order Compliance 6/23/2026 Partial Approval RONNIE MEDINA
Final 6/24/2026 Not Ready for Inspection RONNIE MEDINA
Green Building Final 6/24/2026 Not Ready for Inspection RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Not Ready RONNIE MEDINA
Smoke Detectors 6/24/2026 Not Ready for Inspection RONNIE MEDINA
Final 7/6/2026 OK to Issue CofO RONNIE MEDINA
Green Building Final 7/6/2026 Approved RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 7/6/2026 SGSOV Approved RONNIE MEDINA
Smoke Detectors 7/6/2026 Approved RONNIE MEDINA