1409 S WALGROVE AVE 90066

Certificate Information: 1409 S WALGROVE AVE 90066

Application / Permit
25014-10000-03006
Plan Check / Job No.
B25LA27533
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition (266 sf) and Exterior/Interior Structural Alteration to (E) Single Family Dwelling . Addition [9'-1" x 34'-2"] to the front of the building . Structural Alteration including reframing portion of (E) Roof, install skylights, and revise to cathedral ceiling at portion of living room and kitchen . Interior Alteration including new interior partitions and remodel .
Permit Issued
Issued on 1/5/2026
Issuing Office
Current Status
Issued on 1/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/12/2025 APPLICANT
Assigned to Plan Check Engineer 7/16/2025 GEORGE ALVAREZ
Corrections Issued 7/17/2025 GEORGE ALVAREZ
Plan Check Approved 10/20/2025 GEORGE ALVAREZ
Issued 1/5/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/2/2025 JEANIE LAM
Sewer availability Cleared 9/2/2025 JEANIE LAM
Specific Plan Cleared 9/16/2025 PEDRO AYALA
Grading Pre-Inspection Cleared 9/17/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 9/18/2025 JEANIE LAM

Contact Information

Architect Galambos,, Andrew; Lic. No.: NA31982       ,
Contractor H A S Construction Inc; Lic. No.: 538538-B       ,
Engineer Messiha,, Hany Gamil; Lic. No.: NA56766       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/26/2026 Conditional Approval DAVID FEILER
Deputy Drilled-In Anchors 1/29/2026 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/2/2026 Approved RUBEN RIVAS
Footing/Foundation/Slab 2/2/2026 Partial Approval RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Partial Approval RUBEN RIVAS
Green Building Rough 2/17/2026 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 2/17/2026 Partial Approval RUBEN RIVAS
Deputy Drilled-In Anchors 2/24/2026 Conditional Approval DAVID FEILER
Deputy Wood Construction 2/24/2026 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Approved RUBEN RIVAS
Insulation 3/27/2026 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Approved RUBEN RIVAS
Sewer 4/7/2026 Approved RUBEN RIVAS
ELECTRICAL-Rough 4/30/2026 Approved RUBEN RIVAS
HVAC-Rough 4/30/2026 Approved RUBEN RIVAS
PLUMBING-Rough 4/30/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 5/7/2026 Approved RUBEN RIVAS
Green Building Rough 5/7/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 5/7/2026 Partial Approval RUBEN RIVAS
Insulation 5/12/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 5/12/2026 Approved RUBEN RIVAS