908 E CALIFORNIA AVE 90291
Certificate Information: 908 E CALIFORNIA AVE 90291
- Application / Permit
- 25014-10000-03002
- Plan Check / Job No.
- B25LA27469
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Major remodel and addition to an existing Single-Family Dwelling. Work Per engineered design. NFPA-13D Fire Sprinklered system Throughout.
- Permit Issued
- Issued on 2/27/2026
- Issuing Office
- Current Status
- Issued on 2/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2025 | EDWIN MARTINEZ |
| Corrections Issued | 7/8/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 10/3/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 10/14/2025 | ZAW HAN |
| Plan Check Approved | 12/25/2025 | ZAW HAN |
| Issued | 2/27/2026 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/9/2025 | DAVID URITA |
| Miscellaneous | Cleared | 7/9/2025 | DAVID URITA |
| Miscellaneous | Cleared | 7/9/2025 | DAVID URITA |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2025 | JESUS CISNEROS |
| Coastal Zone | Cleared | 12/10/2025 | JACQUELINE TORRES |
| Coastal Zone | Cleared | 12/10/2025 | JACQUELINE TORRES |
| Disturb/Remove Protected Trees | Cleared | 12/18/2025 | MIGUEL ORNELAS |
| Specific Plan | Cleared | 12/23/2025 | LUIS LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
| Engineer | Herrera,, Edgar E; Lic. No.: NA67603 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/3/2026 | Partial Approval | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 3/4/2026 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/16/2026 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 3/16/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Underground Mechanical | 3/16/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Wood Frame | 3/16/2026 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 4/1/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Approved | RUBEN RIVAS |
| Deputy Wood Construction | 4/8/2026 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Approved | RUBEN RIVAS |
| Gas Test | 4/8/2026 | Partial Approval | RUBEN RIVAS |
| Underground Mechanical | 4/8/2026 | Approved | RUBEN RIVAS |
| Gas Test | 4/15/2026 | Partial Approval | RUBEN RIVAS |
| Underground Mechanical | 4/15/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 4/20/2026 | Approved | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 4/20/2026 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/23/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/23/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/27/2026 | Approved | RUBEN RIVAS |
| Insulation | 4/30/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 5/5/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 5/27/2026 | Approved | RUBEN RIVAS |
| Shower Pan | 5/27/2026 | Approved | RUBEN RIVAS |