1653 W 38TH ST 90062

Certificate Information: 1653 W 38TH ST 90062

Application / Permit
25014-10000-02998
Plan Check / Job No.
B25LA27360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ADDITION TO AND CONVERT OF EXISTING GARAGE TO NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(4). ALL WORK PER WFPP
Permit Issued
Issued on 10/23/2025
Issuing Office
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 7/4/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 10/17/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 10/22/2025 SARKIS HARABEDIAN
Issued 10/23/2025 APPLICANT
CofO in Progress 6/1/2026 SABAS ALONSO
Permit Finaled 6/2/2026 DEROLD HAUFF
CofO Issued 6/2/2026 DEROLD HAUFF
Permit Finaled 6/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/14/2025 DERRICK MAGEE
Community Plan Implem. Overlay Cleared 7/14/2025 MANERI ROMAN
Eng Process Fee Ord 176,300 Cleared 7/14/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 7/14/2025 DERRICK MAGEE
Sewer availability Cleared 7/14/2025 DERRICK MAGEE
Construction near power lines Cleared 10/11/2025 RIDWAN HARDY

Contact Information

Contractor Jb Design & Construction; Lic. No.: 469380-B       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/13/2025 Corrections Issued SABAS ALONSO
Underground Mechanical 11/13/2025 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/17/2025 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/18/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 11/18/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 12/15/2025 Approved SABAS ALONSO
Underground Mechanical 12/15/2025 Partial Approval SABAS ALONSO
Sewer 12/23/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/12/2026 Corrections Issued SABAS ALONSO
Insulation 1/12/2026 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 1/12/2026 Corrections Issued SABAS ALONSO
Shower Pan 1/12/2026 Not Ready for Inspection SABAS ALONSO
Insulation 1/15/2026 Not Ready for Inspection WILLIAM SIERRA
Rough-Elec/Plmb/HVAC 1/15/2026 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 1/21/2026 Approved SABAS ALONSO
Green Building Rough 1/21/2026 Approved SABAS ALONSO
HVAC-Rough 1/21/2026 Approved SABAS ALONSO
PLUMBING-Rough 1/21/2026 Approved SABAS ALONSO
Insulation 1/23/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 1/23/2026 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 2/3/2026 Approved RONNIE MINDANAO
Shower Pan 2/3/2026 Approved RONNIE MINDANAO
Final 5/5/2026 Corrections Issued SABAS ALONSO
Green Building Final 5/5/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 5/5/2026 Approved SABAS ALONSO
ELECTRICAL-Final 5/11/2026 Not Ready for Inspection SABAS ALONSO
Final 5/11/2026 Corrections Issued SABAS ALONSO
HVAC-Final 5/11/2026 Approved SABAS ALONSO
PLUMBING-Final 5/11/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 5/11/2026 Not Ready for Inspection SABAS ALONSO
Final 5/12/2026 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 5/29/2026 Approved SABAS ALONSO
Final 5/29/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 5/29/2026 Approved SABAS ALONSO