1621 S GARTH AVE 90035
Certificate Information: 1621 S GARTH AVE 90035
- Application / Permit
- 25014-10000-02963
- Plan Check / Job No.
- B25LA27017
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: MAJOR REMODEL WITH 2-STORY ADDITION AND NEW ATTACHED GARAGE TO (E) SFD PER ENGINEER DESIGN **13D SPRINKLER REQUIRED**
- Permit Issued
- Issued on 7/22/2025
- Issuing Office
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | KHUONG TRUONG |
| Corrections Issued | 7/8/2025 | KHUONG TRUONG |
| Quality Review Completed | 7/10/2025 | GARO TELMI |
| Applicant returned to address corrections | 7/16/2025 | KHUONG TRUONG |
| Plan Check Approved | 7/22/2025 | KHUONG TRUONG |
| Issued | 7/22/2025 | APPLICANT |
| CofO in Progress | 2/18/2026 | WILBER ROSALES |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
| CofO Issued | 2/24/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/16/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/16/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/2/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/5/2025 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 9/8/2025 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/12/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 10/7/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 10/9/2025 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 10/15/2025 | Approved | EVAN COOPER |
| Shower Pan | 10/15/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 10/21/2025 | Approved | EVAN COOPER |
| Green Building Rough | 10/21/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 10/21/2025 | Approved | EVAN COOPER |
| METHANE-Rough | 10/21/2025 | Approved | EVAN COOPER |
| Structural Steel Frame | 10/21/2025 | Approved | EVAN COOPER |
| Insulation | 10/24/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 10/27/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/10/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 2/10/2026 | Approved | WILBER ROSALES |
| METHANE-Barrier | 2/10/2026 | Approved | WILBER ROSALES |
| METHANE-Subgrade | 2/10/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 2/10/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 2/11/2026 | Approved | WILBER ROSALES |
| Final | 2/17/2026 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 2/17/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 2/17/2026 | Approved | WILBER ROSALES |
| Smoke Detectors | 2/17/2026 | Approved | WILBER ROSALES |