- EPLAN Conversion of exisitng detached garage 314 SF with a 187 SF addition to ADU per engineer design (Ordinance ADU Type, New Construction or Conversion of Existing, LAMC12.22A.33(b)(1))
- Permit Issued
- Issued on 9/24/2025
- Issuing Office
- Current Status
- Issued on 9/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2025 | AUNG SOE |
| Corrections Issued | 7/10/2025 | AUNG SOE |
| Applicant returned to address corrections | 9/9/2025 | AUNG SOE |
| Plan Check Approved | 9/9/2025 | AUNG SOE |
| Issued | 9/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 7/17/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 7/17/2025 | ABEL CASILLAS |
| Construction near power lines | Cleared | 9/3/2025 | RIDWAN HARDY |
Contact Information
| Contractor | South Bay General Construction Llc; Lic. No.: 1134652-B | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/30/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/2/2025 | Corrections Issued | JEFFREY MEAD |
| Deputy Wood Construction | 10/21/2025 | Conditional Approval | JEFFREY MEAD |
| Underground Mechanical | 10/21/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/27/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/27/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 10/27/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 10/27/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 10/27/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/28/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/28/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 10/28/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/28/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/28/2025 | Approved | JEFFREY MEAD |
| Insulation | 11/4/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/4/2025 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 11/4/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 11/10/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/10/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 11/10/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 12/3/2025 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Final | 12/16/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 12/16/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/22/2025 | No Access for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/22/2025 | No Access for Inspection | JEFFREY MEAD |
| Green Building Final | 12/22/2025 | No Access for Inspection | JEFFREY MEAD |
| Green Building Rough | 12/22/2025 | No Access for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 12/22/2025 | No Access for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 12/24/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 12/24/2025 | Partial Inspection | JEFFREY MEAD |
| HVAC-Final | 12/24/2025 | Approved | JEFFREY MEAD |
| Service/Power Release | 12/24/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 1/13/2026 | Approved | WILLIAM SIERRA |
| Service/Power Release | 1/13/2026 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 2/19/2026 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/19/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 2/19/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 2/24/2026 | Partial Approval | JEFFREY MEAD |
| Green Building Final | 2/24/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Required | JEFFREY MEAD |
| Sewer | 2/24/2026 | Approved | JEFFREY MEAD |
| Smoke Detectors | 2/24/2026 | Approved | JEFFREY MEAD |