3926 W SUNSET DR 90027

Certificate Information: 3926 W SUNSET DR 90027

Application / Permit
25014-10000-02948
Plan Check / Job No.
B25LA26920
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Majore remodel with addition to (E) SFD supported on piles. Fire sprinkler NFPA-13D thorughout.
Permit Issued
Issued on 9/23/2025
Issuing Office
Current Status
Issued on 9/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/30/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 FARSHAD ALIMOHAMADI
Corrections Issued 7/5/2025 FARSHAD ALIMOHAMADI
Quality Review Completed 7/18/2025 PRANITA SHAH
Applicant returned to address corrections 9/8/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/9/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 9/11/2025 FARSHAD ALIMOHAMADI
No Progress 9/16/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 9/16/2025 FARSHAD ALIMOHAMADI
Issued 9/23/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 8/4/2025 ADRIAN SANCHEZ
GPI Written Notices Cleared 8/8/2025 FARSHAD ALIMOHAMADI
Grading Pre-Inspection Cleared 8/8/2025 FARSHAD ALIMOHAMADI
Eng Process Fee Ord 176,300 Cleared 8/18/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 8/18/2025 ADRIAN SANCHEZ

Contact Information

Contractor Worman Construction Corp; Lic. No.: 989832-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/23/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 10/24/2025 Corrections Issued BRENDAN MORELLI
Piling/Pier/Caisson 10/24/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 11/4/2025 Approved ENRIQUE MIRELES
Piling/Pier/Caisson 11/4/2025 Approved ENRIQUE MIRELES
Piling/Pier/Caisson 12/2/2025 Approved ENRIQUE MIRELES
Special/Order Compliance 12/17/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Approved ENRIQUE MIRELES
Deputy Wood Construction 2/17/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/18/2026 Approved ENRIQUE MIRELES
HVAC-Rough 2/18/2026 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/18/2026 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 2/20/2026 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 2/20/2026 Approved ENRIQUE MIRELES
HVAC-Rough 2/20/2026 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/20/2026 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 2/20/2026 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 2/20/2026 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 2/23/2026 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/4/2026 Approved ENRIQUE MIRELES
Shower Pan 3/4/2026 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/5/2026 Partial Approval ALEX COLIN
Insulation 3/9/2026 Approved ENRIQUE MIRELES
Drywall Nailing 3/18/2026 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/8/2026 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 5/8/2026 Approved ENRIQUE MIRELES
Final 5/8/2026 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/8/2026 Approved ENRIQUE MIRELES
HVAC-Final 5/8/2026 Approved ENRIQUE MIRELES
PLUMBING-Final 5/8/2026 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/8/2026 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 5/8/2026 Not Ready for Inspection ENRIQUE MIRELES