1859 W 92ND ST 90047

Certificate Information: 1859 W 92ND ST 90047

Application / Permit
25014-10000-02928
Plan Check / Job No.
B25LA26734
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ADDITION TO (E) GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 10/6/2025
Issuing Office
Current Status
Issued on 10/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/6/2025 APPLICANT
Assigned to Plan Check Engineer 7/7/2025 GURUNATH NESARAJAH
Corrections Issued 7/7/2025 GURUNATH NESARAJAH
Applicant returned to address corrections 8/5/2025 SERGIO MUNIZ
Applicant returned to address corrections 9/5/2025 GURUNATH NESARAJAH
Plan Check Approved 9/29/2025 GURUNATH NESARAJAH
Issued 10/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/16/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/23/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/23/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/29/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 9/22/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hwang,, Junho; Lic. No.: S5592 2450 W MAIN ST      ALHAMBRA, CA 91801

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/29/2025 Partial Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 1/22/2026 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 1/22/2026 Partial Approval SALVADOR MARTINEZ
METHANE-Barrier 1/22/2026 Approved SALVADOR MARTINEZ
METHANE-Subgrade 1/22/2026 Approved SALVADOR MARTINEZ
PLUMBING-Rough 1/22/2026 Partial Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 2/4/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 2/6/2026 Approved SALVADOR MARTINEZ
Rough-Elec/Plmb/HVAC 3/19/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 4/1/2026 Approved MICHAEL LEWIS
ELECTRICAL-Rough 4/1/2026 Approved MICHAEL LEWIS
Green Building Rough 4/1/2026 Approved MICHAEL LEWIS
HVAC-Rough 4/1/2026 Partial Approval MICHAEL LEWIS
Interior/Exterior Lathing 4/1/2026 Approved MICHAEL LEWIS
METHANE-Rough 4/1/2026 Approved MICHAEL LEWIS
PLUMBING-Rough 4/1/2026 Approved MICHAEL LEWIS
Insulation 4/7/2026 Approved MICHAEL LEWIS
Drywall Nailing 4/15/2026 Approved ALEX COLIN
Interior/Exterior Lathing 4/15/2026 Approved ALEX COLIN
Sewer 5/29/2026 Conditional Approval SALVADOR MARTINEZ
Underground Mechanical 5/29/2026 Approved SALVADOR MARTINEZ