15143 W LASSEN ST 91345

Certificate Information: 15143 W LASSEN ST 91345

Application / Permit
25014-10000-02925
Plan Check / Job No.
B25LA26721
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) Detached Garage for new Accessory Dwelling Unit per LAMC 12.22A.33(b)(1) . (E) Garage to remain as Garage . Work per Engineered Design .
Permit Issued
Issued on 8/19/2025
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2025 APPLICANT
Assigned to Plan Check Engineer 7/1/2025 FERNANDO FLORES
Corrections Issued 7/3/2025 FERNANDO FLORES
Building Plans Picked Up 7/7/2025 APPLICANT
Plan Check Approved 7/18/2025 AUNG SOE
Issued 8/19/2025 APPLICANT
CofO in Progress 12/17/2025 JENNIFER RABUCHIN
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/7/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 7/7/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/7/2025 MICHAEL BROWN
Sewer availability Cleared 7/7/2025 MICHAEL BROWN

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/27/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/27/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/3/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 9/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/4/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/2/2025 No Access for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/2/2025 No Access for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 10/2/2025 No Access for Inspection JENNIFER RABUCHIN
Pre-Inspection 10/2/2025 No Access for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 10/3/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 10/3/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/3/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/8/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/8/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 10/8/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/8/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/16/2025 Approved JENNIFER RABUCHIN
Insulation 10/16/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 10/22/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/22/2025 Approved JENNIFER RABUCHIN
Shower Pan 10/22/2025 Approved JENNIFER RABUCHIN
Sewer 11/18/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 11/18/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/11/2025 Corrections Issued JENNIFER RABUCHIN
Final 12/11/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/11/2025 Approved JENNIFER RABUCHIN
HVAC-Final 12/11/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 12/11/2025 Approved JENNIFER RABUCHIN
Special/Order Compliance 12/11/2025 Approved JENNIFER RABUCHIN
Pre-Inspection 12/15/2025 No Access for Inspection MATTHEW NELSON
ELECTRICAL-Final 12/17/2025 Approved JENNIFER RABUCHIN
Final 12/17/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/17/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/17/2025 Approved JENNIFER RABUCHIN
Service/Power Release 12/17/2025 Approved JENNIFER RABUCHIN