15143 W LASSEN ST 91345
Certificate Information: 15143 W LASSEN ST 91345
- Application / Permit
- 25014-10000-02925
- Plan Check / Job No.
- B25LA26721
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to (E) Detached Garage for new Accessory Dwelling Unit per LAMC 12.22A.33(b)(1) . (E) Garage to remain as Garage . Work per Engineered Design .
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2025 | FERNANDO FLORES |
| Corrections Issued | 7/3/2025 | FERNANDO FLORES |
| Building Plans Picked Up | 7/7/2025 | APPLICANT |
| Plan Check Approved | 7/18/2025 | AUNG SOE |
| Issued | 8/19/2025 | APPLICANT |
| CofO in Progress | 12/17/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/7/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/7/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 9/3/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 9/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 9/4/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/2/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 10/2/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/2/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 10/2/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/16/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/16/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/22/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/22/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/22/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 11/18/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/18/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 12/15/2025 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 12/17/2025 | Approved | JENNIFER RABUCHIN |
| Final | 12/17/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 12/17/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/17/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/17/2025 | Approved | JENNIFER RABUCHIN |