- eplan: conversion of (e) garage and Unpermitted area to new accessory dwelling unit with addition per LAMC 12.22 A.33(b)(1)3 "Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2)"
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- Issued on 8/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/1/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/11/2025 | ALEC MOUSAKHANIAN |
| Issued | 8/13/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 7/18/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 7/18/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2025 | COLIN LOREDO |
| HPOZ | Cleared | 7/24/2025 | LAMBERT GIESSINGER |
| Construction within easement | Cleared | 8/6/2025 | OSCAR CASTRO |
Contact Information
| Architect | Miller,, Corey William; Lic. No.: C35005 | 3001 POTOMAC AVE LOS ANGELES, CA 90016 |
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 10/20/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 10/24/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/24/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/30/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 11/25/2025 | Conditional Approval | ALEX COLIN |
| Deputy Wood Construction | 12/8/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/16/2026 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 1/16/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 1/16/2026 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/20/2026 | Approved | JEFFREY MEAD |
| Wood Frame | 1/20/2026 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 1/22/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/27/2026 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 1/27/2026 | Approved | JEFFREY MEAD |
| Insulation | 2/4/2026 | Approved | JEFFREY MEAD |
| Drywall Nailing | 2/13/2026 | Approved | JEFFREY MEAD |
| Shower Pan | 2/13/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/11/2026 | Approved | JEFFREY MEAD |
| Green Building Final | 6/3/2026 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 6/3/2026 | Not Ready for Inspection | JEFFREY MEAD |