128 N NORTON AVE 90004

Certificate Information: 128 N NORTON AVE 90004

Application / Permit
25014-10000-02910
Plan Check / Job No.
B25LA26554
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: conversion of (e) garage and Unpermitted area to new accessory dwelling unit with addition per LAMC 12.22 A.33(b)(1)3 "Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2)"
Permit Issued
Issued on 8/13/2025
Issuing Office
Current Status
Issued on 8/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/26/2025 APPLICANT
Assigned to Plan Check Engineer 6/30/2025 MOHAMMAD ESMAILI
Corrections Issued 7/1/2025 MOHAMMAD ESMAILI
Plan Check Approved 8/11/2025 ALEC MOUSAKHANIAN
Issued 8/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/18/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 7/18/2025 COLIN LOREDO
Sewer availability Cleared 7/18/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 7/22/2025 COLIN LOREDO
HPOZ Cleared 7/24/2025 LAMBERT GIESSINGER
Construction within easement Cleared 8/6/2025 OSCAR CASTRO

Contact Information

Architect Miller,, Corey William; Lic. No.: C35005 3001 POTOMAC AVE      LOS ANGELES, CA 90016
Contractor Lannen Construction Inc; Lic. No.: 811038-B       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2025 Approved JEFFREY MEAD
Underground Mechanical 10/20/2025 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 10/24/2025 Approved RONNIE MINDANAO
Footing/Foundation/Slab 10/24/2025 Approved RONNIE MINDANAO
Footing/Foundation/Slab 10/30/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Partial Approval JEFFREY MEAD
Deputy Wood Construction 11/25/2025 Conditional Approval ALEX COLIN
Deputy Wood Construction 12/8/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Approved JEFFREY MEAD
ELECTRICAL-Rough 1/16/2026 Corrections Issued JEFFREY MEAD
HVAC-Rough 1/16/2026 Approved JEFFREY MEAD
PLUMBING-Rough 1/16/2026 Approved JEFFREY MEAD
ELECTRICAL-Rough 1/20/2026 Approved JEFFREY MEAD
Wood Frame 1/20/2026 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 1/22/2026 Approved JEFFREY MEAD
Green Building Rough 1/22/2026 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/27/2026 Partial Approval JEFFREY MEAD
Underground Mechanical 1/27/2026 Approved JEFFREY MEAD
Insulation 2/4/2026 Approved JEFFREY MEAD
Drywall Nailing 2/13/2026 Approved JEFFREY MEAD
Shower Pan 2/13/2026 Approved JEFFREY MEAD
Interior/Exterior Lathing 3/11/2026 Approved JEFFREY MEAD
Green Building Final 6/3/2026 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 6/3/2026 Not Ready for Inspection JEFFREY MEAD