3788 S VICTORIA AVE 90016
Certificate Information: 3788 S VICTORIA AVE 90016
- Application / Permit
- 25014-10000-02831
- Plan Check / Job No.
- B25LA25775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. ADD TO AND CONVERT THE (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/17/2026
- Issuing Office
- Current Status
- Issued on 2/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2025 | SARKIS HARABEDIAN |
| Corrections Issued | 7/3/2025 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 9/10/2025 | PINANK PATEL |
| Plan Check Approved | 12/23/2025 | OMAR GARNICA |
| Issued | 2/17/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/8/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/18/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 12/17/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/17/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Cr Builders Llc; Lic. No.: 1131278-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/27/2026 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 3/2/2026 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 3/4/2026 | Approved | LUIS CASTRO |
| Sewer | 3/10/2026 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 3/10/2026 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 4/7/2026 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 4/7/2026 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 4/7/2026 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 4/7/2026 | Approved | LUIS CASTRO |
| Sewer | 4/7/2026 | Approved | LUIS CASTRO |
| HVAC-Rough | 4/13/2026 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 4/13/2026 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 4/20/2026 | Approved | LUIS CASTRO |
| HVAC-Rough | 4/20/2026 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/22/2026 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 4/22/2026 | Approved | LUIS CASTRO |
| Insulation | 4/22/2026 | Partial Approval | LUIS CASTRO |
| Insulation | 4/24/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 4/29/2026 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/6/2026 | Approved | ALEX COLIN |